Update for Week of July 9
- Lane closings at Glenstone/Kearney intersection should be complete by end of the week
Work Scheduled:
- Installing concrete medians at Kearney Street/Glenstone Avenue intersection
- Building entrances and sidewalks in various locations
- Repairing concrete pavement in areas that did not receive new pavement
- Installing road signs
- Applying pavement striping in areas including Glenstone Avenue/Kearney Street intersection
Traffic Impacts:
- Outside lanes of Glenstone Avenue closed at Kearney Street
- Outside lanes of Kearney Street closed at Glenstone Avenue
- No right turns at Glenstone/Kearney intersection
- Traffic shifts and lane closings when crews stripe pavement at mid-week
- Work complete at Evergreen/Kerr Streets at Glenstone Avenue
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Rebuild the deteriorating concrete pavement on Glenstone Avenue in four separate locations
- At Kerr/Evergreen Street south of I-44
- At Kearney Street
- At the railroad overpass north of Commercial Street
- Between Lombard Street and Page Street
- Sections at Kearney Street and at Evergreen Street under construction from May 29 until early July
- Sections at railroad overpass near Commercial Street and between Lombard Street and Page Street under construction starting in July or August
- Total Project Cost: $3.7 million
- Overall Completion Date: November 1, 2018
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)
(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)
Districts Involved
Southwest
Published On