Route 65: THE REBUILD Phase Two - Springfield

Update for Week of July 9 ? PROJECT STARTS JULY 14
  • I-44 CLOSED at Route 65 in Springfield from 12:01 a.m. Saturday, July 14, until 12:01 a.m. Sunday, July 15
  • Southbound Route 65 at I-44 CLOSED from 12:01 a.m. Saturday, July 14, until late August                                            

Work Scheduled:  

  • Removing southbound Route 65 bridge over I-44 starting early Saturday morning, July 14 

Traffic Impacts:  

  • I-44 CLOSED for 24-Hours: 12:01 a.m. Saturday, July 14, until 12:01 a.m. Sunday, July 15
    • Westbound detour: Northbound Route 65 to Valley Water Mill Road interchange (Farm Road 102) to southbound Route 65 to westbound I-44
    • Eastbound detour: Southbound Route 65 to Division Street to northbound Route 65 to eastbound I-44
    • One eastbound and one westbound lane of I-44 closed at Route 65. Work hours: 11:59 p.m. Saturday until 6 a.m. Sunday
    • ALL lanes of I-44 at Route 65 OPEN by 6 a.m. Sunday, July 15
  • SOUTHBOUND ROUTE 65 CLOSED: 12:01 a.m. Saturday, July 14, until late August
    • Southbound detour: Westbound I-44 to Glenstone Avenue (Exit 80) to eastbound I-44 to southbound Route 65 

(Weather or construction delays could alter the work schedule.) 

Project Summary:

  • Replace southbound Route 65 bridge over I-44
  • Rebuild southbound Route 65 pavement between Valley Water Mill Road (Farm Road 102) and Kearney Street
    • August 6-August 12 – Southbound Route 65 CLOSED between I-44 and Kearney Street
    • August 13-August 21 – Southbound Route 65 CLOSED between Valley Water Mill Road (Farm Road 102) to I-44
  • Rebuild ramps:
    • Rebuild westbound I-44-to-southbound Route 65 ramp
    • Rebuild eastbound I-44-to-southbound Route 65 ramp
    • Rebuild southbound Route 65-to-Kearney Street ramp
    • Rebuild portion of eastbound I-44-to-southbound Route 65 ramp
  • Upgrade guardrail
  • Rebuild shoulders
  • No work planned for northbound Route 65
  • Prime Contractor: Millstone Weber, Inc. of St. Charles, Mo.
  • Completion Date: November 2018 (However, contractor plans to complete project by late August.)
  • Total Project Cost: $4.3 million 

END 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest

(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)

(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)

 

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.