The following is a listing of general highway maintenance and construction work in the mid-Missouri area for the two-week period of July 9-July 20, 2018. Weather conditions may postpone the work schedule. Many projects will include lane closures that could cause delays.
MoDOT reminds motorists to buckle up, slow down, follow posted signs and drive safely through work areas. For more information about a project, please contact MoDOT at 1-888-ASK-MoDOT (275-6636) or visit www.modot.org/central. You can also follow MoDOT’s Central Missouri District on Twitter and Facebook at https://twitter.com/MoDOT_Central and MoDOT Central Missouri District.
All Counties
Daylight Hours
Mowing, striping, brush cutting and guardrail repair continue in various locations. Motorists should travel with care and be alert to slow-moving equipment along the road.
Boone County
Daylight/Overnight Hours
Route 124 between Route B and Route CC – Resurfacing and shoulder improvements are nearing completion. Striping operations will take place the week of July 9.
Route B between Business Loop 70 and Brown Station Road – Roadway resurfacing and sidewalk improvements are nearing completion. Pavement repair between Route 63 and Brown Station Road, as well as the Route 63 entrance and exit ramps, will take place the week of July 9.
Overnight Hours
Interstate 70 between mile marker 125.4 and mile marker 126.4 – Pavement repair in the eastbound lanes will take place Sunday, July 8 and Monday, July 9. One eastbound lane will be open through the work area.
Route 40 between Route UU and Route 5 in Howard County – Resurfacing and shoulder improvements continue.
* Contractors continue paving the three-foot shoulders along the roadway. Roadway resurfacing will begin at the Route 5 intersection the week of July 9. One lane will be open, and a pilot car will guide traffic through the work area. The project is scheduled to be completed in October.
Route 740 (Stadium Boulevard) between Route 763 and Carrie Franke Drive – Pavement marking will take place Wednesday, July 11 and Thursday, July 12. One lane will be open, and crews will flag traffic through the work area.
Route V between Thomas Hill Road and Winn Road – Culvert pipe replacement will take place on Monday, July 9. The road will be closed between 8 p.m. and 6 a.m. Motorists are advised to seek alternate route.
Route OO between East Street and Owens School Road – Culvert pipe replacement will take place on Tuesday, July 10. The road will be closed between 8 p.m. and 6 a.m. Motorists are advised to seek alternate route.
Daylight Hours
Route 63 between Route 22 and Route EE in Randolph County – Roadway resurfacing in the northbound lanes will begin on Monday, July 16. One northbound lane will be open through the work area. The project is scheduled for completion in November.
Route Z between Mount Hope Road and Sexton Lane – Roadway paving will take place Monday, July 9 through Thursday, July 12. One lane will be open, and crews will flag traffic through the work area.
Callaway County
Daylight/Overnight Hours
Route 54 Bridge Improvements
Here is a look at traffic impacts currently in place near the U.S. Route 54 improvement project:
* Guard cable installation on the eastbound and westbound Route 54 from Holts Summit to Route HH in Fulton
* Bridge rehabilitation work on the eastbound Route 54 bridge over Stinson Creek. One eastbound lane of Route 54 will be closed through the work area.
These traffic impacts are scheduled until the end of July.
Daylight Hours
Route A between Interstate 70 and Route B – Pavement patching will take place Monday, July 9 through Thursday, July 19. One lane will be open, and crews will flag traffic through the work area.
Route B between Route 54 and the Montgomery County line – Pavement patching will take place Monday, July 9 through Thursday, July 12. One lane will be open, and crews will flag traffic through the work area.
Route D between Route 94 and Route O – Pavement patching will take place Monday, July 9 through Thursday, July 19. One lane will be open, and crews will flag traffic through the work area.
Route E between Route DD and Old Route 54 – Roadway resurfacing will begin on Wednesday, July 11. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in October.
Camden County
Daylight Hours
Route 5 between Route 7 and Route E in Laclede County – Guardrail installation and replacement and pavement repair continues.
* Paving operations will begin the week of July 9. Occasional lane closures are likely in the work area. The entire project is scheduled for completion in November.
Route JJ between Route H and Route F in Laclede County – Culvert pipe replacement in various locations will take place Monday, July 9 through Thursday, July 12. One lane will be open, and crews will flag traffic through the work area.
Cole County
Daylight/Overnight Hours
Route 54 between Broadway Street and Stadium Boulevard – Roadway resurfacing, pavement repair, guard rail replacement and bridge repair continues.
* The project is in its third stage, which includes rehabilitation of the westbound Route 54 bridges over Stadium Boulevard and Broadway Street and work on the Route 54 on-ramp from the Madison Street bridge beginning July 9.
*During the work, westbound Route 54 will be reduced to one lane 24 hours a day from north of Broadway to south of Stadium.
* The Route 54 on-ramp from Madison Street will also be closed during the work.
The work on Westbound Route 54 and Madison Street exit is scheduled for completion in early August.The entire project is scheduled for completion in November.
Daylight Hours
Route 17 between Route 54 and Route 52 Miller County – Roadway resurfacing and shoulder widening continues.
* Concrete replacement will take place just north of the Saline Creek bridge the week of July 9. Curves will be widened on the north and south sides of the bridge as well.
One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in November.
Route J between Route 50 and Fourth Street – Ditch repair will take place Monday, July 9 through Thursday, July 19. One lane will be open, and crews will flag traffic through the work area.
Route M between Route 50 and Route B – Ditch repair will take place Monday, July 9 through Thursday, July 19. One lane will be open, and crews will flag traffic through the work area.
Cooper County
Daylight Hours
Route 135 between Interstate 70 and Route JJ – Pavement repair will take place Monday, July 16 through Thursday, July 19. One lane will be open, and crews will flag traffic through the work area.
Route BB between Route A and Morgan Street – Sidewalk improvements continue. Much of the work will take place off the roadway. Minimal traffic interruptions are expected.
Crawford County
Overnight Hours
Interstate 44 between Route H and Route ZZ – Pavement repair in the eastbound lanes continues. One eastbound lane will be open through the work area. The project is scheduled for completion in November.
Daylight Hours
Route 19 between Route 8 and Route 49 – Drainage repair will take place Monday, July 9 through Thursday, July 19. One lane will be open, and crews will flag traffic through the work area.
Route 19 between Route O and Route P – Pavement marking will take place Tuesday, July 10 through Thursday, July 12. One lane will be open, and crews will flag traffic through the work area.
Route 49 between Route V and Route Y in Iron County – Drainage repair will take place Monday, July 9 through Thursday, July 19. One lane will be open, and crews will flag traffic through the work area.
Route E between Route 8 and Cave Road – Drainage repair will take place Monday, July 9 through Thursday, July 19. One lane will be open, and crews will flag traffic through the work area.
Route F between Route 19 and Route EE – Pavement patching will take place Tuesday, July 10 through Thursday, July 12. One lane will be open, and crews will flag traffic through the work area.
Route M between Route 8 and Route YY – Pavement repair will take place Monday, July 9 through Thursday, July 19. One lane will be open, and crews will flag traffic through the work area.
Route M between Route 8 and Route VV – Culvert pipe replacement in various locations will take place Monday, July 9 through Thursday, July 19. One lane will be open, and crews will flag traffic through the work area.
Dent County
Daylight/Overnight Hours
Route F over Dry Fork Creek, South of Route NN – Bridge replacement continues. The road is closed. Motorists should use the signed detour around the work area. The project is scheduled for completion in August.
Daylight Hours
Route 32 between Route 72 and Route 63 in Texas County – Roadway microsurfacing continues.
* Striping and surface repair operations are scheduled for the week of July 9. One lane will be open and crews will guide traffic through the work area. The project is scheduled for completion in the fall.
Gasconade County
Daylight Hours
Route 19 between Route 28 and Route 50 – Shoulder addition and asphalt paving continues. One lane will be open, and crews will flag traffic through the work area.
Route T over the Bourbeuse River, south of Tea Road – Bridge maintenance will take place Monday, July 9 through Thursday, July 12. One lane will be open, and crews will flag traffic through the work area.
Howard County
Overnight Hours
Route 40 between Route 5 and Route UU in Boone County – Resurfacing and shoulder improvements continue.
* Contractors continue paving the three-foot shoulders along the roadway. Roadway resurfacing will begin at the Route 5 intersection the week of July 9. One lane will be open, and a pilot car will guide traffic through the work area. The project is scheduled to be completed in October.
Daylight Hours
Route 3 between County Road 215 and County Road 217 – Culvert pipe repair will take place on Tuesday, July 10. One lane will be open, and crews will flag traffic through the work area.
Route 5 between View Drive and Route V in Chariton County – Drainage repair will take place Monday, July 16 through Thursday, July 19. One lane will be open, and crews will flag traffic through the work area.
Route E between County Road 207 and County Road 305 – Culvert pipe replacement will take place on Wednesday, July 11. The road will be closed from 8 a.m. until 4 p.m. Motorists are advised to seek an alternate route around the area.
Route H over Salt Fork Creek, south of County Road 204 – Bridge maintenance will take place Monday, July 16 through Thursday, July 19. One lane will be open, and crews will flag traffic through the work area.
Laclede County
Overnight Hours
Interstate 44 between Route 133 and Route D in Phelps County – Roadway resurfacing continues.
* The westbound exit ramp at mile marker 172 will close on Monday, July 9 to begin bridge repair work on the ramp. The ramp will re-open in mid-August. Motorists are advised to use the signed detour routes around the ramp closure.
* Guardrail repair and replacement will take place in various locations in the eastbound and westbound lanes the week of July 9.
* Paving operations in the eastbound lanes will continue the week of July 9. One eastbound lane will be open through the work area.
The entire project is scheduled for completion in August, 2019.
Interstate 44 between Elm Street and Route 133 – Pavement repair in the eastbound lanes continues. One eastbound lane will be open through the work area. The project is scheduled for completion in November.
Daylight Hours
Route 5 between Route E and Route 7 Camden County – Guardrail installation and replacement and pavement repair continues.
* Paving operations will begin the week of July 9. Occasional lane closures are likely in the work area. The entire project is scheduled for completion in November.
Route 5 between Route C and Farmer’s Lane – Roadway resurfacing and shoulder widening continues. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in August.
Route 32 between Route 5 and Route 17 in Texas County – Roadway resurfacing and shoulder widening continues. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in November.
Route O between Route Z and Route TT – Pavement repair will take place Monday, July 9 through Thursday, July 12. One lane will be open, and crews will flag traffic through the work area.
Route JJ between Route F and Route H in Camden County – Culvert pipe replacement in various locations will take place Monday, July 9 through Thursday, July 12. One lane will be open, and crews will flag traffic through the work area.
Route PP between Route C and Route J – Culvert pipe replacement in various locations will take place Monday, July 16 through Thursday, July 19. One lane will be open, and crews will flag traffic through the work area.
Maries County
Daylight Hours
Route 42 between Route 63 and Route 17 in Miller County – Roadway resurfacing, shoulder addition, and guardrail installation continue.
* Crews will pave asphalt the week of July 9. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in November.
Route 42 over the Gasconade River, east of County Road 335 – Scour repair will begin on Monday, July 9. Minimal traffic interruptions are expected. The project is scheduled for completion in August.
Route BB between Route 133 and Route 42 in Miller County – Pavement patching will take place Monday, July 9 through Thursday, July 19. One lane will be open, and crews will flag traffic through the work area.
Route EE between Route 28 and County Road 407 – Culvert pipe replacement will take place on Tuesday, July 10. One lane will be open, and crews will flag traffic through the work area.
Miller County
Daylight/Overnight Hours
Route A over Tavern Creek, east of Route PP – Bridge replacement continues. The road is closed. Motorists are advised to seek alternate route. The project is scheduled for completion in mid-August.
Daylight Hours
Route 17 between Route 52 and Route 54 in Cole County – Roadway resurfacing and shoulder widening continues.
* Concrete replacement will take place just north of the Saline Creek bridge the week of July 9. Curves will be widened on the north and south sides of the bridge as well. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in November.
Route 42 between Route 17 and Route 63 in Maries County – Roadway resurfacing, shoulder addition, and guardrail installation continue.
* Crews will pave asphalt the week of July 9. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in November.
Route H between Route 17 and Marys Home Road – Roadway resurfacing continues. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in November.
Route W at Village Marina Road – Culvert pipe repair will take place Monday, July 9 through Wednesday, July 11. One lane will be open, and crews will flag traffic through the work area.
Route BB between Route 42 and Route 133 in Maries County – Pavement patching will take place Monday, July 9 through Thursday, July 19. One lane will be open, and crews will flag traffic through the work area.
Business Route 54 at Eastview Drive – Drainage repair will take place Monday, July 16 through Wednesday, July 18. One lane will be open, and crews will flag traffic through the work area.
Moniteau County
Daylight Hours
Route K between Bybee Road and Wieneke Branch Road – Culvert pipe replacement will take place Wednesday, July 11 and Thursday, July 12. One lane will be open, and crews will flag traffic through the work area.
Morgan County
Daylight Hours
Route BB over Middle Richland Creek, south of Self Chapel Road – Bridge replacement continues. The road is closed. Motorists are advised to seek alternate route. The project is scheduled for completion in August.
Route PP over Messer Creek, east of Route D – Bridge replacement continues. The road is closed. Motorists are advised to seek alternate route. The project is scheduled for completion in August.
Osage County
Daylight Hours
Route A between Route 50 and Route W – Pavement patching will take place Monday, July 9 through Thursday, July 19. One lane will be open, and crews will flag traffic through the work area.
Route 50 between Route U and Loose Creek Highway – Concrete repair in the eastbound and westbound lanes will take place Monday, July 9 and Tuesday, July 10. One eastbound lane and one westbound lane will be open through the work area.
Route 50 between Route 63 and County Road 602 – Concrete repair in the eastbound and westbound lanes will take place Wednesday, July 11 and Thursday, July 12. One eastbound lane and one westbound lane will be open through the work area.
Phelps County
Daylight/Overnight Hours
Interstate 44 between Route D and Route 133 in Laclede County – Roadway resurfacing continues.
* The westbound exit ramp at mile marker 172 will close on Monday, July 9 to begin bridge repair work on the ramp. The ramp will re-open in mid-August. Motorists are advised to use the signed detour routes around the ramp closure.
* Guardrail repair and replacement will take place in various locations in the eastbound and westbound lanes the week of July 9.
* Paving operations in the eastbound lanes will continue the week of July 9. One eastbound lane will be open through the work area.
The entire project is scheduled for completion in August, 2019.
Route B over the Bourbeuse River, north of County Road 1400 – Bridge replacement continues. Much of the work will take place off the roadway. Minimal traffic interruptions are expected. The project is scheduled for completion in the fall.
Route D over the Burlington Northern/Sante Fe Railroad, east of Interstate 44 – Bridge replacement continues. Much of the work will take place off the roadway. Minimal traffic interruptions are expected. The project is scheduled for completion in the fall.
Pulaski County
Daylight/Overnight Hours
Interstate 44 between Route 133 in Laclede County and Route D in Phelps County – Roadway resurfacing continues.
* The westbound exit ramp at mile marker 172 will close on Monday, July 9 to begin bridge repair work on the ramp. The ramp will re-open in mid-August. Motorists are advised to use the signed detour routes around the ramp closure.
* Guardrail repair and replacement will take place in various locations in the eastbound and westbound lanes the week of July 9.
* Paving operations in the eastbound lanes will continue the week of July 9. One eastbound lane will be open through the work area.
The entire project is scheduled for completion in August, 2019.
Daylight Hours
Route 17 between Business Loop 44 and Beaufort Road – Pavement patching will take place Monday, July 9 through Thursday, July 12. One lane will be open, and crews will flag traffic through the work area.
Route AB between Route 17 and Route 133 – Pavement patching will take place Monday, July 9 and Tuesday, July 10. One lane will be open, and crews will flag traffic through the work area.
Washington County
Daylight Hours
Route M between Route 21 and Route BB in St. Francois County – Ditch repair will take place Tuesday, July 17 through Thursday, July 19. One lane will be open, and crews will flag traffic through the work area.
Route U between Route M and Route BB in St. Francois County – Chip sealing the roadway surface to extend pavement life will take place on Monday, July 16. Motorists should expect to encounter loose gravel on the road surface for several days after the seal coat is complete. At that time, crews will sweep the roadway. Motorists should expect delays and lower their speeds through the area. One lane will be open, and crews will flag traffic through the work area.
Route BB between Route C and Janes Creek Road – Chip sealing the roadway surface to extend pavement life will take place on Monday, July 16. Motorists should expect to encounter loose gravel on the road surface for several days after the seal coat is complete. At that time, crews will sweep the roadway. Motorists should expect delays and lower their speeds through the area. One lane will be open, and crews will flag traffic through the work area.
MoDOT encourages motorists to log on to www.modot.org/central to comment on their experiences traveling through highway work zones.
###