I-44 OPEN at Route 65 and Southbound Route 65 at I-44 Remains CLOSED in Springfield
- I-44 OPEN both directions at Route 65 in Springfield
- Southbound Route 65 CLOSED at I-44 until late August
When:
- I-44 OPEN at Route 65
- Southbound Route 65 CLOSED until late August
Traffic Impacts:
- One lane of I-44 open in each direction. All four lanes open by 6 a.m. Sunday, July 15
- Southbound Route 65 at I-44 CLOSED until late August
- Detour: Westbound on I-44 to Glenstone Avenue (Exit 80) to eastbound I-44 to southbound Route 65
- Westbound I-44-to-southbound Route 65 ramp CLOSED until late August
- Detour: Westbound Route 744/Kearney Street (Exit 84) to southbound Route 65
- Southbound Route 65-to-eastbound I-44 ramp CLOSED until late August
- Detour: Westbound on I-44 to Glenstone Avenue (Exit 80) to eastbound I-44 to southbound Route 65
- All detours signed
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Replace southbound Route 65 bridge over I-44
- Rebuild southbound Route 65 pavement between Valley Water Mill Road (Farm Road 102) and Kearney Street
- Rebuild ramps:
- Rebuild westbound I-44-to-southbound Route 65 ramp
- Rebuild eastbound I-44-to-southbound Route 65 ramp
- Rebuild southbound Route 65-to-Kearney Street ramp
- Rebuild portion of eastbound I-44-to-southbound Route 65 ramp
- Upgrade guardrail
- Rebuild shoulders
- No work planned for northbound Route 65
- Prime Contractor: Millstone Weber, Inc. of St. Charles, Mo.
- Completion Date: November 2018 (However, contractor plans to complete project by mid-August.)
- Total Project Cost: $4.3 million
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)
(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)
Districts Involved
Southwest
Published On