Route 65: THE REBUILD Phase Two - Springfield

Update for Week of July 23
  • Southbound Route 65 at I-44 CLOSED until late August; ramps to southbound Route 65 CLOSED
  • Work focused on building bridge columns along I-44 at Route 65 for new southbound Route 65 bridge
  • Speed limit on I-44 at Route 65 REDUCED to 50 mph. Drivers urged to slow down through work zone.                                            

Work Scheduled:  

  • Building bridge columns for new southbound Route 65 bridge along I-44
  • Removing pavement from westbound I-44-to-southbound Route 65 and southbound Route 65-to-eastbound I-44 ramps
  • Removing pavement from southbound Route 65 on either side of bridge over I-44
  • Installing storm drain pipes in various locations 

Traffic Impacts:  

  • SOUTHBOUND ROUTE 65 CLOSED until late August
    • Southbound detour: Westbound I-44 to Glenstone Avenue (Exit 80) to eastbound I-44 to southbound Route 65
    • Southbound detour: Westbound on Route 744/Kearney Street (Exit 84) to south Route 65
  • RAMP CLOSINGS until late August
    • Westbound I-44-to-southbound Route 65
    • Southbound Route 65-to-eastbound I-44
    • Ramp detour: Westbound I-44 to Glenstone Avenue (Exit 80) to eastbound I-44 to southbound Route 65. Also, westbound I-44 to westbound Route 744 (Exit 84)/Kearney Street to southbound Route 65
  • Nighttime lane closings on I-44 at times. One lane in each direction will remain open. Work hours: 9 p.m. to 6 a.m. 

(Weather or construction delays could alter the work schedule.) 

Project Summary:

  • Replace 50-year old, poor condition southbound Route 65 bridge over I-44
  • Rebuild 1970s-era, deteriorating southbound Route 65 pavement between Valley Water Mill Road (Farm Road 102) and Kearney Street
    • August 6-August 12 – Southbound Route 65 CLOSED between I-44 and Kearney Street
    • August 13-August 21 – Southbound Route 65 CLOSED between Valley Water Mill Road (Farm Road 102) to I-44
  • Rebuild deteriorating ramps:
    • Rebuild westbound I-44-to-southbound Route 65 ramp
    • Rebuild eastbound I-44-to-southbound Route 65 ramp
    • Rebuild southbound Route 65-to-Kearney Street ramp
    • Rebuild portion of eastbound I-44-to-southbound Route 65 ramp
  • Upgrade guardrail
  • Rebuild shoulders
  • No work planned for northbound Route 65
  • Prime Contractor: Millstone Weber, Inc. of St. Charles, Mo.
  • Completion Date: November 2018 (However, contractor plans to complete project by late August.)
  • Total Project Cost: $4.3 million 

END 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest

(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)

(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.