Route 65: THE REBUILD Phase Two - Springfield

Update for Week of July 30
  • I-44 CLOSED in one direction at a time over two separate nights during the week
  • Southbound Route 65 CLOSED at I-44 until late August for bridge reconstruction                                            

Work Scheduled:  

  • Installing bridge girders and other components for southbound Route 65 bridge over I-44
  • Grading work for westbound I-44-to-southbound Route 65 and southbound Route 65-to-eastbound I-44 ramps
  • Grading work for southbound Route 65 on either side of I-44
  • Installing storm drain pipes in various locations 

Traffic Impacts:  

  • I-44 CLOSED at night in one direction at a time:
    • Westbound I-44 CLOSED. Work hours: 10 p.m. to 6 a.m. Monday into Tuesday, July 30-31
      • Detour: Northbound Route 65 to Valley Water Mill Rd (FRD 102) to southbound Route 65 to westbound I-44
    • UPDATED DATE - Eastbound I-44 CLOSED. Work hours: 10 p.m. to 6 a.m. Thursday into Friday, Aug. 2-3
      • Detour: Southbound Route 65 to Division Street to northbound Route 65 to eastbound I-44
  • SOUTHBOUND ROUTE 65 CLOSED until late August
    • Southbound detour: Westbound I-44 to Glenstone Avenue (Exit 80) to eastbound I-44 to southbound Route 65
    • Southbound detour: Westbound on Route 744/Kearney Street (Exit 84) to southbound Route 65
  • ROUTE 65/I-44 INTERCHANGE RAMP CLOSINGS until late August
    • Westbound I-44-to-southbound Route 65
    • Southbound Route 65-to-eastbound I-44
      • Ramp detours:
        • Westbound I-44 to Glenstone Avenue (Exit 80) to eastbound I-44 to southbound Route 65.
        • Westbound I-44 to westbound Route 744 (Exit 84)/Kearney Street to southbound Route 65
  • Nighttime lane closings on I-44 at times. One lane in each direction remains open. Work hours: 9 p.m. to 6 a.m.
  • Nighttime lane closings on northbound Route 65 at I-44 at times. One lane remains open. Work hours: 9 p.m. to 6 a.m.
  • I-44 speed limit at Route 65: 50 mph

 

 

 (Weather or construction delays could alter the work schedule.)

 Project Summary:

  • Replace 50-year old, poor condition southbound Route 65 bridge over I-44
  • Rebuild 1970s-era, deteriorating southbound Route 65 pavement between Valley Water Mill Road (Farm Road 102) and Kearney Street
    • August 6-August 12 – Southbound Route 65 CLOSED between I-44 and Kearney Street
    • August 13-August 21 – Southbound Route 65 CLOSED between Valley Water Mill Road (Farm Road 102) to I-44
  • Rebuild deteriorating ramps:
    • Rebuild westbound I-44-to-southbound Route 65 ramp
    • Rebuild eastbound I-44-to-southbound Route 65 ramp
    • Rebuild southbound Route 65-to-Kearney Street ramp
    • Rebuild portion of eastbound I-44-to-southbound Route 65 ramp
  • Upgrade guardrail along southbound and northbound Route 65
  • Rebuild shoulders
  • No work planned for northbound Route 65
  • Prime Contractor: Millstone Weber, Inc. of St. Charles, Mo.
  • Completion Date: November 2018 (However, contractor plans to complete project by late August.)
  • Total Project Cost: $4.3 million 

END 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest

(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)

(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)

 

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.