Route 65: THE REBUILD Phase Two - Springfield

Update for Week of August 13
  • Southbound Route 65 CLOSED between Valley Water Mill Road (FRD 102) and I-44 for new pavement construction August 12-19
  • Southbound Route 65 REOPENS between I-44 and Kearney Street on Sunday night, August 12                                            

Work Scheduled:  

  • Removing and rebuilding original southbound Route 65 concrete pavement between Valley Water Mill Road and I-44
  • Allowing concrete to cure for new driving surface/bridge deck on southbound Route 65 over I-44
  • Installing new guardrail in areas along northbound and southbound Route 65 at I-44
  • Paving shoulders along southbound Route 65 in areas between Valley Water Mill Road and Kearney Street 

Traffic Impacts:  

  • SOUTHBOUND ROUTE 65 BETWEEN I-44 AND KEARNEY STREET REOPENS BY 10 P.M. ON SUNDAY NIGHT, AUGUST 12
    • Eastbound I-44-to-southbound Route 65 ramp reopens
    • Southbound Route 65-to-Kearney Street ramp reopens
  • SOUTHBOUND ROUTE 65 CLOSED BETWEEN VALLEY WATER MILL ROAD AND I-44 AUGUST 12-19
    • Southbound Route 65-to-westbound I-44 ramp CLOSED
    • Valley Water Mill Road-to-southbound Route 65 ramp CLOSED
    • Closing Period: 10 p.m. Sunday, August 12, until 10 p.m. Sunday, August 19
    • Signed Detour for Southbound Route 65: Westbound on Greene County Route AA to southbound Greene County Route H/Glenstone Avenue to I-44 (Exit 80)
    • Congestion expected at Glenstone Avenue/I-44 interchange. Drivers who can avoid this area are encouraged to find alternate routes.
  • SOUTHBOUND ROUTE 65 AT I-44 CLOSED UNTIL LATE AUGUST
    • Westbound I-44-to-southbound Route 65 closed
    • Southbound Route 65-to-eastbound I-44 closed
      • Signed Detours:
        • I-44 to Glenstone Avenue (Exit 80) to eastbound I-44 to southbound Route 65.
        • I-44 to westbound Route 744 (Exit 84)/Kearney Street to southbound Route 65
      • Nighttime ramp closings:
        • Eastbound I-44-to-southbound Route 65
        • Southbound Route 65-to-Kearney Street
        • Work hours: 10 p.m. to 6 a.m. Friday, August 17
        • Signed detours in place
      • Nighttime lane closings on I-44 at times. One lane in each direction remains open. Work hours: 9 p.m. to 6 a.m.
      • Nighttime lane closings on northbound Route 65 at I-44 at times. One lane remains open. Work hours: 8 p.m. to 6 a.m.
      • I-44 speed limit at Route 65: 50 mph 

(Weather or construction delays could alter the work schedule.)

Project Summary:

  • July 14-Late August
    • Replace 50-year old, deteriorating southbound Route 65 bridge over I-44
    • Rebuild westbound I-44-to-southbound Route 65 ramp
    • Rebuild southbound Route 65-to-eastbound I-44 ramp
  • August 5-August 12
    • Rebuild original 1970s-era southbound Route 65 concrete pavement between I-44 and Kearney Street
    • Rebuild southbound Route 65-to-Kearney Street ramp
    • Rebuild portion of eastbound I-44-to-southbound Route 65 ramp
  • August 12-August 19
    • Rebuild original 1970s-era southbound Route 65 concrete pavement between Valley Water Mill Road (FRD 102) and I-44
  • Upgrade guardrail
  • Rebuild shoulders
  • No work planned for northbound Route 65
  • Prime Contractor: Millstone Weber, Inc. of St. Charles, Mo.
  • Completion Date: November 2018 (However, contractor plans to complete project by late August.)
  • Total Project Cost: $4.3 million

 END 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest

(Follow MoDOT's Southwest District:
Facebook | Twitter | Instagram |YouTube)

(For timely traffic information in the Springfield area, visit
www.ozarkstraffic.com)

 

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.