Route 65: THE REBUILD Phase Two - Springfield

Update for Week of August 20
  • New southbound Route 65 bridge over I-44 scheduled to OPEN by late week
  • Southbound Route 65 scheduled to OPEN between Valley Water Mill Road (FRD 102) and I-44 by late Sunday evening, Aug. 19                                            

Work Scheduled:  

  • Building walls along southbound Route 65 bridge over I-44
  • Paving westbound I-44-to-southbound Route 65 and southbound Route 65-to-eastbound I-44 ramps
  • Paving shoulders along southbound Route 65 between Valley Water Mill Road and Kearney Street
  • Installing guardrail in areas
  • Applying pavement striping on new southbound Route 65 bridge over I-44
  • Cleanup work throughout project 

Traffic Impacts:  

  • SOUTHBOUND ROUTE 65 BETWEEN VALLEY WATER MILL ROAD AND I-44 scheduled to OPEN BY LATE SUNDAY, AUG. 19
    • Southbound Route 65-to-westbound I-44 ramp OPEN
    • Valley Water Mill Road-to-southbound Route 65 ramp CLOSED until Monday, Aug. 20
  • SOUTHBOUND ROUTE 65 AT I-44 CLOSED UNTIL LATE IN THE WEEK
    • Westbound I-44-to-southbound Route 65 closed
    • Southbound Route 65-to-eastbound I-44 closed
      • Signed Detours:
        • I-44 to Glenstone Avenue (Exit 80) to eastbound I-44 to southbound Route 65.
        • I-44 to westbound Route 744 (Exit 84)/Kearney Street to southbound Route 65
      • Nighttime lane closings on I-44 at times. One lane in each direction remains open. Work hours: 9 p.m. to 6 a.m.
      • Nighttime lane closings on northbound Route 65 at I-44 at times. One lane remains open. Work hours: 8 p.m. to 6 a.m.
      • I-44 speed limit at Route 65: 50 mph 

(Weather or construction delays could alter the work schedule.)

Project Summary:

  • July 14-Week of August 20
    • Replace 50-year old, deteriorating southbound Route 65 bridge over I-44
    • Rebuild westbound I-44-to-southbound Route 65 ramp
    • Rebuild southbound Route 65-to-eastbound I-44 ramp
  • August 5-August 12
    • Rebuild original 1970s-era southbound Route 65 concrete pavement between I-44 and Kearney Street
    • Rebuild southbound Route 65-to-Kearney Street ramp
    • Rebuild portion of eastbound I-44-to-southbound Route 65 ramp
  • August 12-August 19
    • Rebuild original 1970s-era southbound Route 65 concrete pavement between Valley Water Mill Road (FRD 102) and I-44
  • Upgrade guardrail
  • Rebuild shoulders
  • No work planned for northbound Route 65
  • Prime Contractor: Millstone Weber, Inc. of St. Charles, Mo.
  • Completion Date: November 2018 (However, contractor plans to complete project by late August.)
  • Total Project Cost: $4.3 million 

END 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest

(Follow MoDOT's Southwest District:
Facebook | Twitter | Instagram |YouTube)

(For timely traffic information in the Springfield area, visit
www.ozarkstraffic.com)

 

Districts Involved
Southwest