Valley Water Mill Road to Southbound Route 65 Ramp OPEN to Traffic
What: Valley Water Mill Road ramp to southbound Route 65 open to traffic following pavement reconstruction
When: 2:45 p.m. today (Monday, Aug. 20)
Project Summary:
- July 14-Week of August 20
- Replace 50-year old, deteriorating southbound Route 65 bridge over I-44
- Rebuild westbound I-44-to-southbound Route 65 ramp
- Rebuild southbound Route 65-to-eastbound I-44 ramp
- August 5-August 12
- Rebuild original 1970s-era southbound Route 65 concrete pavement between I-44 and Kearney Street
- Rebuild southbound Route 65-to-Kearney Street ramp
- Rebuild portion of eastbound I-44-to-southbound Route 65 ramp
- August 12-August 19
- Rebuild original 1970s-era southbound Route 65 concrete pavement between Valley Water Mill Road (FRD 102) and I-44
- Upgrade guardrail
- Rebuild shoulders
- No work planned for northbound Route 65
- Prime Contractor: Millstone Weber, Inc. of St. Charles, Mo.
- Completion Date: November 2018 (However, contractor plans to complete project by late August.)
- Total Project Cost: $4.3 million
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)
(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)