Glenstone Avenue Pavement Rebuild

Update for Week of September 10
  • Glenstone Avenue reduced to one lane in each direction and traffic shifted to southbound lanes at railroad bridge north of Commercial Street 

Work Scheduled:  

  • Removing concrete pavement in northbound lanes of Glenstone Avenue underneath railroad bridge 

Traffic Impacts:

  • Northbound lanes of Glenstone Avenue CLOSED underneath railroad bridge north of Commercial Street
  • Glenstone Avenue reduced to one lane in each direction and traffic shifted to southbound side underneath railroad bridge
  • Delays and traffic congestion are expected
  • Drivers urged to avoid area if possible unless they need to visit businesses in the area 

(Weather or construction delays could alter the work schedule.) 

Project Summary:

  • Rebuilding the deteriorating, 1950’s-era concrete pavement on Glenstone Avenue in four separate locations
    • At Kerr/Evergreen Street south of I-44 - COMPLETE
    • At Kearney Street - COMPLETE
    • At the railroad underpass north of Commercial Street
    • Between Lombard Street and Page Street
  • Total Project Cost: $3.7 million
  • Overall Completion Date: November 1, 2018 

END 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest

(Follow MoDOT's Southwest District:
Facebook | Twitter | Instagram |YouTube)

(For timely traffic information in the Springfield area, visit
www.ozarkstraffic.com)

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.