Update for Week of September 10
- Glenstone Avenue reduced to one lane in each direction and traffic shifted to southbound lanes at railroad bridge north of Commercial Street
Work Scheduled:
- Removing concrete pavement in northbound lanes of Glenstone Avenue underneath railroad bridge
Traffic Impacts:
- Northbound lanes of Glenstone Avenue CLOSED underneath railroad bridge north of Commercial Street
- Glenstone Avenue reduced to one lane in each direction and traffic shifted to southbound side underneath railroad bridge
- Delays and traffic congestion are expected
- Drivers urged to avoid area if possible unless they need to visit businesses in the area
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Rebuilding the deteriorating, 1950’s-era concrete pavement on Glenstone Avenue in four separate locations
- At Kerr/Evergreen Street south of I-44 - COMPLETE
- At Kearney Street - COMPLETE
- At the railroad underpass north of Commercial Street
- Between Lombard Street and Page Street
- Total Project Cost: $3.7 million
- Overall Completion Date: November 1, 2018
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)
(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)
Districts Involved
Southwest
Published On