Proposed improvements for Route 67 between New Halls Ferry to I-270 are:
- Resurface approximately four miles of pavement.
- Upgrade the existing sidewalks and curb ramps to meet ADA requirements.
- Construct new sidewalks in front of Phillips 66, Firestone Complete Auto Care, and the utility substation.
- Replace existing entrances to meet ADA requirements.
- Reconstruct traffic signals at Trotterway Dr., Target entrance, North Waterford Dr./Thunderbird Ave., New Florissant Rd., St. Jean St., West Washington St./Charbonier Rd., and Elm Grove Ave.
- Replace the acceleration lane on Lindbergh Blvd. northbound between Taylor Rd. and Elm Grove Rd. that was removed as part of the I-270 improvements.
- Make connection between existing sidewalk along the north side of Lindbergh Blvd. and the existing switchback for the Great Rivers Greenway Sunset Greenway Trail at the bridge just east of Patterson Rd.
- Replace all ground mounted and affected overhead corridor signage.
Project Timeline
Complete
Conceptual Design
Complete
Public Meeting #1
May 23, 2024
MERS Goodwill Excel Center
3180 N Hwy 67, Florissant, MO 63033
MERS Goodwill Excel Center
3180 N Hwy 67, Florissant, MO 63033
Complete
Public Meeting #2
January 16, 2025
Hazelwood Civic Center East, 4-6 p.m.
8969 Dunn Rd., Hazelwood, MO 63042
Hazelwood Civic Center East, 4-6 p.m.
8969 Dunn Rd., Hazelwood, MO 63042
In Progress
Right of Way Process Begins
Winter 2024
Not Started
Contract Awarded
Spring 2026
Not Started
Construction Begins
Spring 2026
Project Completed
Late Fall 2027
What is the cost of this project?
The estimated cost of this project is $11.3 million.
Project Strip Maps
Below are links to project strip maps that were shared during the Jan. 16 public meeting. The maps outline proposed areas of improvement. After viewing the maps, please provide any feedback you may have by clicking on the COMMENT FORM link.