Counties Impacted
Greene
Webster
Route Impacted
125
60
Work Type
Intersection Improvements
Completed

Project Timeline

October 29, 2018
Public meeting held to show plans for new interchange
milestone_icon
August 20, 2019
Public meeting to gather feedback on two interchange options
milestone_icon
April-May 2020
Virtual (online) public meeting to gather additional feedback on preferred concept for new interchange
milestone_icon
October 26, 2021
Virtual Public Hearing to show Preliminary Design Plans for new interchange
milestone_icon
2022
Secure land needed for project
milestone_icon
2022
Final project design work completed
milestone_icon
4:30 p.m. - 6 p.m. Thursday, January 19
Public Meeting at Logan-Rogersville High School, 300 N. Missouri Boulevard (Route 125 north of Route 60), to show Final project design work for new interchange
milestone_icon
2023-2024
Construction of new interchange
milestone_icon

Project Facts:

  • Build interchange at U.S. Route 60/Route 125 intersection
  • Build interchange ramps for safe access between U.S. Route 60 and Route 125
  • Build outer road from Missouri Route 125 to Farm Road 229 and Farm Road 243

Project Information:

  • Contractor: Capital Paving & Construction LLC, Jefferson City
  • Completion date: November 1, 2024
  • Total estimated Construction cost: $20.4 million
  • Project is a cost-share with the City of Rogersville and Greene County

NEWS RELEASES/PROJECT UPDATES