Counties Impacted
Franklin
Route Impacted
100
Work Type
Bridge Rehabilitation
What is the current situation?

The Missouri Department of Transportation is implementing a project to address the aging pavement and other corridor upgrades. 

The project will take place on Route 100 from east of East Fifth Street to 0.2 miles west of Route OO and on Spur 100 over Interstate 44, and bridge rehabilitation over Missouri Eastern Railway, east of route M. Pavement resurfacing, pavement repairs, guardrail, signing & signal upgrades, and bridge rehabilitation on the eastbound and westbound Route 100 over the Missouri Eastern Railway, just east of Route M, will be a part of the corridor upgrades. 

Project Milestones

Complete
Project Advertised
November 2024
milestone_icon
Complete
Letting Date

December 10, 2024 

milestone_icon
Complete
Project Award Date

January 8, 2025

The project was awarded to N.B. West Contracting Company. 

milestone_icon
Not Started
Anticipated Construction Start Date

February 10, 2025

milestone_icon
Not Started
Anticipated Construction Completion Date

November 24, 2025

milestone_icon

Project Contacts

Contact Photo
Aaron Groff
Aaron Groff, P.E.
Title
Project Manager
Department
St. Louis District
Contact Info

Transportation Project Manager, Franklin & Jefferson County Area 

(314) 453-1876

Aaron.Groff@modot.mo.gov

Contact Photo
Jordan Dalaviras
Jordan Dalaviras
Title
Area Liaison, Franklin and Jefferson County
Department
St. Louis District
Contact Info

Phone: (314) 453-5021
E-mail: jordan.dalaviras@modot.mo.gov

 

Frequently Asked Questions

What the anticipated traffic impacts?

MoDOT will be completing bridge rehabilitation over the eastbound and westbound Union Pacific Railroad bridge and the Route 100 bridge. The railroad bridge rehabilitation will take approximately 4-5 months to complete once construction begins. There will be westbound and eastbound single lane drops during off-peak hours near the Union Pacific Railroad bridge. The eastbound bridge redeck over Union Pacific Railroad will require eastbound Route 100 traffic to be reduced to one lane while work is being completed. MoDOT will contact emergency responders, local schools, and businesses prior to any traffic closures and notify the public of any potential delays. 

What is the total cost of construction?

The total cost of construction on the project is estimated at $8.8 million.