Counties Impacted
Holt
Project Status
Planning Phase
Route Impacted
U.S. Route 159

Proposed Project Timeline

In Progress
Design Phase

MoDOT has brought on HNTB Corporation to design a new bridge over the Little Tarkio Creek.

Not Started
Contractors Bid on Projects

This emergency contract is currently scheduled in the June 21, 2019 letting. At that time contractors will be able to submit competitive bids for the project.

Not Started
Contract Awarded

The Missouri Highways and Transportation Commission will review all bids and may award the contract to the lowest qualifying bidder at their July 2019 meeting.

Not Started
Notice to Proceed

The Notice to Proceed date is the earliest the contractor may begin work on the project. The current Notice to Proceed date is Aug. 5, 2019. Weather and flooding may play a role in this timeframe.

Not Started
Construction Underway

A construction schedule will be established by the contractor and the Missouri Department of Transportation after the contract has been awarded. By contract, the contractor will have 80 working days and 112 calendar days to complete the project. Weather and flooding may play a role in these timeframes.

Not Started
Completion Date

By contract, the project must be complete by Dec. 1, 2019. Again, weather and flooding may impact that date.