Project Summary

The Southwest District’s Kaysinger Basin Bridge Bundle will replace or rehabilitate up to 25 poor condition bridges in west central Missouri and bring them up to current standards. The majority of these bridges are on two-lane rural routes. These bridges connect and serve the communities and citizens of rural west central Missouri in Bates, Benton, Cedar, Henry, Hickory, St. Clair, and Vernon. On average, these bridges have been in place for 70 years.

Project Goals:

  1. Safely deliver the project within the programmed budget of $38 million.
  2. Maximize the number of locations to be addressed while providing quality, low maintenance structures and roadway approaches.
  3. Minimize impacts to the public through diligent construction efforts, flexibility in scheduling, and proactive communication.
  4. Deliver the project utilizing a diverse work force.
  5. Complete the project on or before November 15, 2027

Project Milestones

Complete
Project Advertisement
July 1, 2024
milestone_icon
Complete
Request for Letters of Interest
Firms interested in receiving Kaysinger Basin Bridge Bundle information must send a letter of interest to MoDOT by July 26, 2024

You may e-mail your letter of interest to: kaysingerbridgebundle@modot.mo.gov

milestone_icon
Complete
Industry Meeting
August 1, 2024
1-3 p.m., CDT, Benson Convention & Exposition Center
1008 E. Sedalia Ave., Clinton, MO 64735

Video recording of industry meeting available after August 1, 2024

milestone_icon
Complete
Release Request for Qualifications (RFQ)
August 2024
milestone_icon
Complete
Statement of Qualifications (SOQ) Due
September 23, 2024
10 a.m., CDT
milestone_icon
Complete
Statement of Qualifications (SOQ) Shortlist
September 2024

The pre-qualified teams are as follows:

  • Capital – Horner & Shifrin Team
    • Capital Paving and Construction, Horner & Shifrin​, EFK Moen​, Geotechnology​, Shafer & Hines
  • ESS Team
    • Emery Sapp & Sons, Bartlett & West
  • Lunda Team
    • Lunda Construction Company​, Parsons Transportation Group, Terracon Consultants, HZ United

There are still opportunities for additional consultants and subcontracting firms to be added to each team.

milestone_icon
Complete
Public Meeting
October 3, 2024
4-6 p.m., Benson Convention & Exposition Center
1008 E. Sedalia Ave., Clinton, MO 64735
milestone_icon
Not Started
Issue Request for Proposals (RFP)
October 2024
milestone_icon
Not Started
Proposals Due
January 2025
milestone_icon
Not Started
Missouri Highways & Transportation Commission Selection of Design-Build Team
February 2025
milestone_icon
Not Started
Project Completion
November 2027
milestone_icon

NEWS RELEASES

Frequently Asked Questions:

How will you maintain traffic and access to my property or business during construction?

Bridges are expected to be closed while they are under construction, however access to adjacent properties will be maintained throughout that time. Some bridges in this project may be near other improvements on state-maintained highways. Should the need arise, the contractors will coordinate to minimize traffic conflicts and restrictions to properties.

Will construction interfere with emergency vehicle access?

Emergency vehicles will have access to all adjacent properties while each bridge location is under construction. Since the bridges will be closed and inaccessible while work is performed, the contractor will notify and coordinate with emergency services during the construction period.

Will traffic be detoured during construction of the project?

All bridges are expected to be closed while under construction. Of the 25 total bridges in the project, 15 have high enough traffic volumes to require signed detours.

When will construction begin?

Construction is anticipated to start in the summer of 2025. All construction activity is expected to be completed by November 15, 2027.

How long will construction last at each bridge?

After the construction project is awarded, a determination will be made on the amount of work to be done at each bridge. This will also determine the length of closure at each bridge. Once those determinations are made, the project’s web page will be updated. Currently, the project is anticipated to be awarded in early Spring 2025 and completed by November 2027.

How do I ask a question or leave feedback about this project?

MoDOT will be hosting a virtual (online) public meeting September 30-October 14. During that time you may return to this website and fill out a feedback form found here. You also may send us an e-mail at swcr@modot.mo.gov or call us at (417) 895-7600.

Webform