Counties Impacted
St. Louis
Route Impacted
70
Work Type
Conceptual Study
Planning Phase

Project Summary

The Missouri Department of Transportation is conducting a conceptual study to identify potential improvements for two adjacent sections of I-70 between the Missouri River and North Hanley Road.  

Segment 1: Missouri River to west of US 67 (Lindbergh Blvd.)

  • Goal of Segment 1 - Identify potential improvements to the safety and operations of the corridor that might influence the programmed 2024-2028 Statewide Transportation Improvement Program (STIP). The Improve I-70 STL Conceptual Study from the Missouri River to Lindbergh Blvd. reflects multiple “take care of the system” projects along the corridor.

Segment 2: West of US 67 (Lindbergh Blvd.) to North Hanley Rd.

  • Goal of Segment 2 - Identify potential improvements to the safety and operations of the corridor, identify corridor needs, and coordinate with proposed improvements by local partners.

Anticipated Outcomes 

Some of the outcomes of the study will likely include: 

  • The purpose and need for various improvements. 
  • Goals, objectives, and evaluation measures for this corridor. 
  • Alternative strategies to address identified problems. 
  • An analysis of possible impacts of these alternatives in terms of environmental, transportation, and financial impacts. 
  • An evaluation of how each alternative addresses the problems, goals, and objectives for the corridor. 

Funding for Potential Projects

  • MoDOT has identified partial funding for the potential needs in Segment 1 (FY2027) beyond the in-kind replacement of the designated I-70 bridge locations (I-270 interchange & MO 180 [St Charles Rock Road] over I-70).
  • Segment 2 does not have a project in the current 2024-2028 STIP.
  • The remaining needs in Segment 1 and all of Segment 2 are in the annually updated High Priority Unfunded Needs (HPUN) list.
PRINTABLE FACT SHEET

Project Milestones

Complete
I-70 Planning and Environmental Linkages (PEL) Study
Final Report in 2018

Study to set a vision and strategic plan for the future of the I-70 corridor.

milestone_icon
Complete
Purpose and Need
Fall 2023/Winter 2024

Data Collection, public outreach, identify purpose, needs and project goals.

PUBLIC MEETING #1

December 14, 2023

Bridgeton Recreation Center

VIRTUAL MEETING/PROJECT SURVEY

Dec. 14, 2023 - Jan. 4, 2024

If you were not able to attend the Dec. 14 meeting, you may participate virtually by reviewing the displays below and completing the PROJECT SURVEY.  The survey will be available through Jan. 4, 2024. 

 

milestone_icon
In Progress
Alternate Development and Screening
Spring 2024
milestone_icon
Not Started
Public Meeting #2
Summer 2024
milestone_icon
Not Started
Recommend Alternatives
Summer 2024
milestone_icon
Not Started
Approved Conceptual Study Report
Fall 2024
milestone_icon

Conceptual Study Project Area

Embed
Summary

The GREEN area outlines Segment 1 of the project, which is from the Missouri River to just west of Route 67 (Lindbergh).

The RED area outlines Segment 2 of the project, which is from Lindbergh to North Hanley Rd.

Is Responsive
Embed Code

 

 

 

 

 

 

These display boards provide information on the project and were shared during Public Meeting #1 on Dec. 14.  If you were not able to attend the meeting, you may participate virtually by reviewing the displays and completing the PROJECT SURVEY.  The survey will be available through Jan. 4, 2024. 

Project Leaders

Contact Photo
Photo of Tabitha Locke
Tabitha Locke
Title
Area Engineer, North St. Louis County
Department
St. Louis District
Contact Info

Office:  (314) 453-1749
Email:  Tabitha.Locke@modot.mo.gov

Contact Photo
Photo of Lisa Kuntz
Lisa Kuntz
Title
Transportation Project Manager
Contact Info

St. Louis District
Office:  314-568-7252
Email:  lisa.kuntz@modot.mo.gov