Counties Impacted
Franklin
Route Impacted
44
Work Type
Weigh Station Improvements
In Progress

Project Summary

The Missouri Department of Transportation will be upgrading the westbound St. Clair weigh scale site (1032 N Service Rd W, St Clair, MO 63077) in Franklin County. The 1950's westbound weigh scale site was closed for renovations in October 2023. Shortly after closing, the westbound weigh scale operations were transferred over to the eastbound weigh scale site. Currently, the eastbound weigh scale site is open for operations. Construction on the westbound weigh scale site is ongoing through 2024. MoDOT anticipates reopening the westbound weigh scale site in Mid-2027.

The project is in combination with a pavement resurfacing, signing, and guardrail project on Interstate 44 from the Crawford County Line to 0.5 miles east of the Route 30 overpass in St. Clair. The Interstate 44 project will be awarded in Fiscal 2027 and will include improvements to St. Clair rest area and weigh scales.

 

Project Milestones

Complete
Westbound Weigh Scales Closed
October 2023

The first phase of the weigh scales project began. 

MoDOT closed the westbound weigh scales.

  • The Missouri State Highway Patrol vacated the westbound weigh scales building and moved over to eastbound weigh scales while work is being completed on the westbound weigh scales. 
milestone_icon
In Progress
Phase 1 -- Westbound Weigh Scale Facility Renovations
Construction 2024
  • Removed 10-foot single axle scale and westbound weigh scale building.
  • Construct a new 110-foot static scale, scale house and inspection building.
milestone_icon
In Progress
Phase 2 -- Westbound Weigh Scale Parking Lot Improvements
  • Design -- September 2024 - March 2025
  • Project Advertised -- April 10, 2025
  • Letting Date -- May 16, 2025
  • Project Award -- June 4, 2025
  • Construction Begins -- as early as July 2025
  • Construction Completion -- End of 2025 

 

milestone_icon
Not Started
Phase 3 -- Westbound Weigh Scale Ramp Improvements
Extend ramp lengths for safety improvements
  • Project Advertised -- July 2026
  • Letting Date -- August 2026
  • Project Award -- September 2026
  • Construction Begins -- as early as October 2026
  • Construction Completion -- Mid-2027
milestone_icon
Not Started
Phase 4 -- Eastbound Weigh Scale Site Closure/Repurposing
Eastbound weigh scale closure / convert to truck parking
  • Eastbound weigh scale closure -- Mid-2027 

    (Once westbound weigh scale site is reopened)

  • Opening of new truck parking lot -- TBD
milestone_icon

What's currently happening?

Last year, during October 2023, MoDOT coordinated with the Missouri State Highway Patrol (MSHP) to close the westbound weigh scale site and MSHP moved over to the eastbound weigh scale site to continue their operations. Subsequently as the MSHP resumes their daily work operations out of the eastbound weigh scale site, renovation to westbound scale site is underway. These renovations consist of a new 110-foot static scale, scale house, inspection building, upgraded lighting/signing, and a new parking lot. 

A demolition plan to remove the 1950's masonry block weigh scale building was a part of the first series of projects pertaining to the weigh scale sites on Interstate 44 in St. Clair.  Following the site preparation, an award for the construction of the new 110-foot static scale, scale house and inspection building was issued. The previous westbound site only had a 10-foot single scale axle, causing semi-trucks to have to pull up and be weighed on each axle.

Currently, we are working on the design of the new parking lot site improvements.

Frequently Asked Questions

Why are the Weigh Scales useful?

Weigh scale facilities are located on interstate and U.S. highway routes to ensure commercial motor vehicles comply with the laws, rules, and regulations of Missouri. Fixed scale locations are selected based on the volume of commercial motor vehicles operating on interstate or U.S. routes in a particular area. To read more about weigh stations, view MoDOT's Engineering Policy Guide

Why is the I-44 St. Clair westbound Weigh Scale site closed?

The site was closed in October 2023 in order to reconstruct a new scale, scale house, new inspection building, parking lot and ramp improvements.

When will the eastbound weigh scale site renovations begin?

After the westbound weigh scale site is opened, tentative Mid-2027, the eastbound weigh scale site will be permanently closed, scale and building demolished and will be converted to a truck parking lot only. This will allow more safe locations for trucks to park. 

 

Project Contacts

Contact Photo
Aaron Groff
Aaron Groff, P.E.
Title
Project Manager
Department
St. Louis District
Contact Info

Transportation Project Manager, Franklin & Jefferson County Area 

(314) 453-1876

Aaron.Groff@modot.mo.gov

Contact Photo
Jordan Dalaviras
Jordan Dalaviras
Title
Area Liaison, Franklin and Jefferson County
Department
St. Louis District
Contact Info

Phone: (314) 453-5021
E-mail: jordan.dalaviras@modot.mo.gov