I-229 Moving Forward Timeline V1

May 24, 2018

MoDOT Initiated Environmental Study of the I-229 corridor. Hg Consult was brought in to facilitate the Environmental Assessment.

2018-present

Stakeholder meetings Throughout the I-229 Moving Forward Environmental Assessment (EA) process, the EA team has met with stakeholders including, but not limited to: Businesses within, and in the region, of the I-229 corridor Agricultural community (farmers, grain elevators, etc.) Freight industry (truck drivers, major shippers, ag haulers, etc.) C...

Oct. 9, 2018

Public Meeting #1 - Community, stakeholders, and the public gathered together to consider the needs and priorities of the Environmental Assessment and the I-229 Corridor.

Nov. 1, 2018

Agency Scoping Meeting was held with federal, state, and local governmental units and federally-recognized tribal representatives that have an interest in the project. 

2018-2019

Development and analysis of Initial Alternatives. Twenty alternatives were developed: 18 'build' alternatives, one (1) rehabilitate existing structure alternative, and a 'no-build' alternative required by the Federal Highway Administration (FHWA) to be carried forward as a baseline comparison.

April 4, 2019

Public Meeting #2 - The 20 Initial Alternatives were presented to the public in an open-house format at Remington Nature Center. Public comments were taken at the meeting and via email.

2019-2020

Development of Reasonable Alternatives. The study team took the feedback from Public Meeting #2 and the detailed analysis of the Initial Alternatives and developed six (6) Reasonable Alternatives.

2020-2022

Detailed Analysis of the six (6) Reasonable Alternatives.

October 2020

The St. Joseph Area Transportation Study Organization, the local metropolitan planning organization (MPO), introduced a new alternative.

2020-2022

Detailed analysis of the new alternative presented by the MPO.

May 2022

Newly-elected St. Joseph Mayor John Josendale proposes new alternative on the same alignment of the current I-229 Double-Decker Bridge.

May-June 2022

Detailed analysis of new alignment proposed by Mayor Josendale.

COMING SOON - Summer 2022

Public Meeting #3 - Website relaunch An open-house style public meeting and website relaunch are planned for mid-Summer 2022. The public meeting and website will bring the community up-to-date on where the I-229 Moving Forward EA  stands, which alternatives are still being considered and why they're still being considered, and allow the public...

NEXT STEPS

After Public Meeting #3, the EA team will finalize the Environmental Assessment document for presentation to FHWA, select a preferred alternative based on analysis, stakeholder feedback and public feedback, and present the Recommended Preferred Alternative at a formal public hearing. After the hearing, FHWA will consider the Recommended Preferred A...