Counties Impacted
Greene
Project Status
Planning Phase

Project Facts:

  • Install roundabout at four-way intersection of Greene County Route ZZ & Farm Road 182 to improve safety and traffic flow
  • Installing a 10 foot multi-use path on the northeast, southeast, and southwest portions of the roundabout
  • Approximately 8,100 vehicles per day use the intersection - 4% is truck traffic

Construction: Spring 2023

Estimated total project cost: $1.3 million

Traffic Impacts:

  • Intersection to remain OPEN during most of the project

  • Intersection may be CLOSED intermittently, but not for long periods of time. Electronic message boards and news releases will warn the pubic of closures.

  • No signed detour planned for the project

  • Drivers urged to use alternate routes during construction to avoid the work zone

Project Updates