Project Facts:
- Install roundabout at four-way intersection of Greene County Route ZZ & Farm Road 182 to improve safety and traffic flow
- Installing a 10 foot multi-use path on the northeast, southeast, and southwest portions of the roundabout
-
Approximately 8,100 vehicles per day use the intersection - 4% is truck traffic
Construction: Spring 2023
Estimated total project cost: $1.3 million
Traffic Impacts:
-
Intersection to remain OPEN during most of the project
-
Intersection may be CLOSED intermittently, but not for long periods of time. Electronic message boards and news releases will warn the pubic of closures.
-
No signed detour planned for the project
- Drivers urged to use alternate routes during construction to avoid the work zone