This $26 million design-build project will replace up to 41 bridges in northern Missouri, and was enabled by receipt of a $20.7 million federal grant under the Competitive Highway Bridge Program. MoDOT’s original application for the grant which contains the project information can be found here. For more information, contact Project Director Jeff Gander at FARM@modot.mo.gov.

Solicitation for Owner Engineer: https://www.modot.org/modot-solicitations-rfq

    Counties Impacted
    Adair
    Lewis
    Macon
    Schuyler
    Scotland
    Shelby
    Warren
    Atchison
    Chariton
    Gentry
    Grundy
    Harrison
    Linn
    Livingston
    Putnam
    Sullivan
    Worth
    Project Status
    Planning Phase

    PROCUREMENT SCHEDULE

    Complete
    Project Advertisement
    October 15, 2020
    Complete
    Industry Meeting (Virtual)/RFQ Release
    November 16, 2020

    Virtual meeting will be held using WebEx
    Event address for attendees: https://modot.webex.com/modot/onstage/g.php?MTID=e4fea267db258b600528f68422b6faef9
    To join by phone call 1-408-792-6300 
    Access code 132 922 2060

    Complete
    SOQ’s Due
    December 14, 2020
    Complete
    SOQ Shortlist
    December 23, 2020
    Not Started
    RFP Release
    January 12, 2021
    Not Started
    One-on-One Technical Meetings
    January through March
    Not Started
    Proposals Due
    April 6, 2021
    Not Started
    Award at MHTC Meeting
    May 2021
    • Design/Build Teams Selected to Compete for Bridge Replacements

      12/23/2020

      HANNIBAL – The Fixing Access to Rural Missouri (FARM) bridge program will replace several bridges primarily in northern Missouri.  “These bridges will be built using the design-build procurement method,” said Missouri Department of Transportation...

    • North Missouri Rural Bridges Funded for Replacement

      10/19/2020

      HANNIBAL, Mo – Several rural bridges in northern Missouri will be replaced over the next few years thanks to a grant from the Federal Highway Administration.  “These bridges all have the same issues – they are weight restricted, supported by timber...

    The following teams were selected to further develop their proposals on the project:

    Capital - HDR

    Clarkson - Burns & McDonnell

    Emery Sapp & Sons - Parsons

    Lehman - Wilson

    OCCI – Benesch

    The FARM Bridge Team will release the Request for Proposals (RFP) on January 12, 2021.  “This means these five teams will receive our formal request to submit their proposals to design and construct these bridges,” Gander explained.

     

    PROJECT GOALS:

    1. Safely deliver the project within the program budget of $25.99 million on or before Oct. 31, 2023.
    2. Use innovation to maximize the number of locations to be addressed.
    3. Provide quality long-lasting structures.
    4. Minimize public inconvenience through increased construction speed and flexibility in scheduling.
    Embed
    Is Responsive
    Embed Code