Exit 93 Interchange: Alternates

Strategic Goals for Project

MoDOT considered 5 primary factors when developing alternates for the reconfiguration, including: 

  • SIMPLIFY ACCESS & MERGING MOVEMENTS: Simplify access and merging movements for motorists traveling from US 61 to I-55 southbound.
  • BRIDGE REPLACEMENT: Replace the existing US 61 southbound bridge over I-55.
  • SIMPLIFY CONNECTIONS: Reduce driver confusion at Exit 93A/93B by simplifying connections.
  • LEVEL OF SERVICE: Improve level of service for all vehicle types over the design year.
  • BRIDGE CLEARANCE & FLOODING ISSUES: Improve bridge clearance and flooding issues at I-55 and MO 74.

Alternate Descriptions with Advantages and Disadvantages

Alternate A: Diverging Diamond Interchange

Click Here to View Aerial

Watch Simulation

  • US 61 southbound movement will be two lanes through the interchange.
  • US 61 northbound will be one lane across the bridge.
  • MO 74 will be realigned to connect into the west side of the DDI.
  • US 61 and Silver Springs intersection will be upgraded to a 2-lane roundabout in an effort to improve safety. Access to current arterial routes will remain.
  • The existing MO 74 connection under I-55 would be eliminated.

Advantages

  • Conventional interchange ramps reduce confusion by aligning with driver expectation.
  • Improved merging opportunity for I-55 southbound.
  • MO 74 realignment provides a more direct connection.
  • Supports heaviest traffic movements.
  • 2 phase signals improve operation and reduce delays.
  • Reduces wrong-way movements to I-55.
  • Similar interchange being used in Center Junction on I-55 at Exit 99.

Disadvantages

  • Requires traffic signals. 
  • Off-ramp traffic can’t re-enter the freeway for motorists who take wrong exit.

Alternate B: Dogbone Interchange

Click Here to View Aerial

Watch Simulation

  • Western roundabout is 2 lanes to accommodate for heavy traffic flow to I-55 southbound.
  • Eastern roundabout is 1 lane to US 61 northbound and 2 lanes for US 61 southbound.
  • I-55 northbound to US 61 northbound will bypass the roundabout in a dedicated, free-flow lane.
  • MO 74 will be realigned into the western roundabout. 
  • US 61 and Silver Springs intersection will be upgraded to a 2-lane roundabout in an effort to improve safety. Access to current arterial routes will remain.
  • The existing MO 74 connection under I-55 would be eliminated.

Advantages

  • Roundabouts eliminate need for traffic signals and offer safety benefits over traditional intersections.
  • Improved merging opportunity for I-55 southbound.
  • MO 74 realignment provides a more direct connection.
  • Similar to conventional interchange layout.
  • Off-ramp traffic can easily re-enter the freeway for motorists that take wrong exit.
  • Crashes are less severe at roundabouts than at signalized intersections.

Disadvantages

  • Can take motorists longer to learn how to use roundabouts.

Alternate C: Foldover Interchange

Click Here to View Aerial

Watch Simulation

  • MO 74 will be realigned into the interchange and connect to the roundabout.
  • Motorists traveling from US 61 southbound to I-55 southbound will travel through the folded loop ramp and merge onto I-55.
  • Motorists traveling from US 61 southbound to I-55 northbound will gain access to the entrance ramp at the Silver Springs roundabout.
  • US 61 and Silver Springs intersection will be upgraded to a 2-lane roundabout in an effort to improve safety. Access to current arterial routes will remain.
  • The existing MO 74 connection under I-55 would be eliminated.

Advantages

  • Elimination of northbound ramp intersection reduces crash exposure.
  • Roundabouts eliminate need for traffic signals and offer safety benefits over traditional intersections.
  • Extended merging opportunity for I-55 southbound.
  • MO 74 realignment has smaller footprint with improved access to parcels west of I-55.

Disadvantages

  • Less direct access from MO 74 to I-55 northbound.
  • Loop ramp offers slower travel speeds and shorter merge opportunity near the intersection prior to the I-55 merge.
  • Access from I-55 northbound to MO 74 westbound would require a U-turn at the Silver Springs roundabout.
  • Additional bridge needed for I-55 southbound exit ramp.

Alternate D: Minimum Build

Click Here to View Aerial

  • Maintains the existing interchange configuration.
  • Replaces the US 61 southbound bridge to MO 74 and I-55.

Advantages

  • Lowest cost

Disadvantages

  • Does not address connectivity, safety or congestion issues