Updated 12/1/2022: The bridges over Moss Creek and Route 10, both south of Carrollton, are currently under construction and scheduled to be complete by the end of December 2022.

The expansion joints, driving surfaces and substructures of seven bridges along U.S. Route 24 in Carroll County are in need of rehabilitation.

Counties Impacted
Carroll
Project Status
In Progress
Route Impacted
U.S. Route 24

Project Progress

Complete
Planning & Design Phase

MoDOT's Planning and Design team designed a project which will rehabilitate seven bridges in Carroll County along U.S. Route 24. The project will repair expansion joints, repair the substructure and replace the epoxy wearing surface on the bridges.

Complete
Contract Letting, Award & Notice to Proceed

The projects to rehabilitate the seven bridges on Carroll County U.S. Route 24 were part of the April 2022 letting where contractors submitted competitive bids on the project bundle. The Missouri Highways and Transportation Commission awarded the $6,123,090.85 project to Capital Paving & Construction, Inc. at their May 2022 meeting. At that time they gave the contractor a July 5, 2022 Notice to Proceed. This is the earliest date the contractor could begin work.

In Progress
Project Construction

UNDER CONSTRUCTION:

  • Moss Creek Drainage Ditch Bridge on U.S. Route 24, approx. 4 miles south of Missouri Route 10, Aug. 15, 2022 through December 2022. Temporary traffic signals in place around-the-clock.
  • Missouri Route 10, Outer Road 24 and Norfolk Southern Bridge on U.S. Route 24/65 just south of Carrollton, Aug. 31, 2022 through mid-December 2022. Temporary traffic signals in place around-the-clock.
    • Ramp from Route 10 to northbound U.S. Route 24/65 CLOSED at this location, Aug. 31, 2022 through mid-December 2022.

The contractor is working with the railroads and MoDOT to determine the full construction schedule. At this time, construction of the remaining bridges is planned for 2023.

 

 

Location of Bridges Included in this Project

Embed
Is Responsive
Embed Code

Frequently Asked Questions:

Q: Will the road be closed during construction?

A: The project was designed to be completed under staged construction where only one lane is closed at a time. One lane of U.S. Route 24 should remain open, with restrictions, throughout construction.

 

Q: Who can I contact if I have further questions?

A: Questions about the project may be directed to MoDOT's Customer Service team at NWCR@modot.mo.gov or by phone at 888 ASK MODOT (1-888-275-6636).

 

Q: How can I stay updated on the project's progress?

A: Sign up for project-specific updates using the form below.

Project NEws

Webform
Sign up for email updates:
*
*
*

For more information about this or other MoDOT projects, please contact our 24-hour Customer Service line at 888 ASK MODOT (1-888-275-6636).