The John Jordan “Buck” O’Neil Memorial Bridge (formerly the Broadway Bridge), is a triple arch bridge carrying U.S. Highway 169 over the Missouri River and serving as a key regional connection between downtown Kansas City and communities north of the river. While safe, the bridge, which opened in 1956, is nearing the end of its projected lifespan. Even though the bridge underwent a short-term rehabilitation to extend its service life in 2018, a new bridge is needed to provide a crossing that will support continued use well into the future. So the Missouri Department of Transportation along with the City of Kansas City, Missouri, worked together to procure the $220 million dollars (that includes a $25 million federal grant) for this future transportation facility to improve regional and local system performance. Massman-Clarkson, A Joint Venture, is the design-build contractor chosen for the project - expected to be completed in 2024.
The current timeline for the project is as follows:
- Environmental Assessment Concluded: May 2020
- Request For Proposal Sent: August 2020
- Project Awarded: February 2021
- Construction Began: July 2021
- Anticipated Project Completion: December 2024
We need your input!
What makes you slow down in work zones? Please take a few minutes to complete this survey and give us a better idea of the tools, strategies and other factors that play a role in your speed through a work zone: https://missouri.qualtrics.com/jfe/form/SV_2cwRbLZmHC8G5sq"
Districts Impacted
Traffic Impacts
Crews will set up a flagging operation on Richards Rd., just north of the roundabout, near NW Harlem Rd. from 9:00am until 4:00pm, daily, beginning Tuesday, March 1 and continuing until Friday, April 1 for utility work
*****CANCELED*****
Traffic Impacts set to begin March 7, 2022 - Long-term and short-term:
- Crews will close northbound I-35 from 12th St. to eastbound I-70 (275 days)
- Crews will close northbound I-35 to westbound I-70 (275 days)
- Crews will close the ramp from westbound I-670 to the 12th (275 days)
- Crews will close the eastbound I-70 exit ramp to Broadway Blvd. (2-3 weeks)
- Crews will close eastbound I-70 from Beardsley Rd. exit ramp to the entrance ramp of northbound I-35 to eastbound I-70 (3 days)
- Crews will close the ramp from southbound US 169 to southbound I-35 (3 days)
Crews will close northbound I-35 from 12th to eastbound I-70, tentatively beginning Monday, March 7 and continuing for approximately 275 days for the construction of a new retaining wall along I-35 and for a new bridge over 6th St.
Crews will also close northbound I-35 to westbound I-70 during the same period for bridge rehabilitation work
Project Updates
-
Various closures scheduled as part of Buck O'Neil bridge project continue this week
CLAY/JACKSON COUNTIES – Crews will be making the following traffic changes as part of the construction of the new U.S. 169 Buck O’Neil Bridge over the Missouri River. These closures are for girder setting. All work is weather permitting.
Tuesday...
-
Various closures scheduled as part of Buck O'Neil bridge project continue next week
CLAY/JACKSON COUNTIES – Crews will be making the following traffic changes as part of the construction of the new U.S. 169 Buck O’Neil Bridge over the Missouri River. These closures are for girder delivery. Please note that some information has...
-
Schedule change: Various closures scheduled as part of Buck O'Neil bridge project continue this week
CLAY/JACKSON COUNTIES – Crews will be making the following traffic changes as part of the construction of the new U.S. 169 Buck O’Neil Bridge over the Missouri River. These closures are for girder delivery. Please note that some information has...
-
Various closures scheduled as part of Buck O'Neil bridge project continue next week
CLAY/JACKSON COUNTIES – Crews will be making the following traffic changes as part of the construction of the new U.S. 169 Buck O’Neil Bridge over the Missouri River. These closures are for girder delivery. Please note that some information has chang...
-
Schedule Change: Various closures scheduled as part of Buck O'Neil bridge project beginning June 13
CLAY/JACKSON COUNTIES – Crews will be making the following traffic changes as part of the construction of the new U.S. 169 Buck O’Neil Bridge over the Missouri River. These closures are for girder delivery. Please note that some information has chang...
About the Buck O'Neil Bridge
The year the Broadway (Buck O'Neil) Bridge Opened
Number of cars that use it daily

New Traffic Pattern
See the new traffic pattern for the John Jordan “Buck” O’Neil Memorial Bridge (formerly the Broadway Bridge), a key regional connection between downtown Kansas City and communities north of the river.