Proposed improvements to three bridges along Route 67 are to:
- Replace bridge deck over Coldwater Creek east of New Halls Ferry Rd. and add compliant sidewalks across the bridge on the north and south side.
- Replace bridge deck over Coldwater Creek east of Patterson Rd. and add compliant sidewalks across the bridge on the north and south side.
- Clean, repair, and overlay bridge deck over Taylor/Lynn Haven Rd.
Project Timeline
MERS Goodwill Excel Center
3180 N Hwy 67, Florissant, MO 63033
When will the right of way process begin?
No right of way is needed for this project.
How much will this project cost?
The estimated cost of the project is $7.9 million.
Will there be any impacts to traffic?
The Route 67 bridge over Coldwater Creek near Walmart will be the first to be impacted. At least one lane of traffic will be maintained in both directions. Bridge work is anticipated to be complete in late summer 2025.
The Route 67 bridge over Coldwater Creek near Patterson Rd. is expected to cause daily congestion. At least one lane of traffic will be maintained in both directions during construction. Construction is anticipated to be complete by summer 2026.
The Route 67 bridge over Taylor Rd./Lynn Haven Ln. is anticipated to cause daily congestion. At least one lane of traffic will be maintained on Route 67 during construction. Various detours will be used throughout construction to maintain access to Taylor Rd. and Lynn Haven Ln. The anticipated detours are below. Click HERE to view/print both detour maps on one page.