Counties Impacted
Franklin
Route Impacted
50
Work Type
Pavement Resurfacing
Completed

What is this project?

The project consists of resurfacing, guardrail,  ADA upgrades, and replacing crossroad pipes on U.S. Route 50 from West Outer Independence Road to Missouri Route 47. Raised shoulders will be converted into sidewalks with curb ramps being upgraded for ADA compliance. In addition, drainage upgrades will be done and existing traffic signals within the project limits will be upgraded. The cost of the project is $6.94 million.

Project Timeline

Complete
Public Information Meeting
February 15, 2022

View Project Displays Below

milestone_icon
Complete
Right of Way Takings
milestone_icon
Complete
Project Advertised
October 2022
milestone_icon
Complete
Project Award Date
December 2022
milestone_icon
Complete
Construction Begins
February 2023
milestone_icon
Complete
Project Completed
Summer 2024
milestone_icon

What are the anticipated impacts?

Lane closures will be done in order to complete resurfacing. MoDOT will work with business owners and residents to ensure that access is available during construction. For Right of Way, only Temporary Construction Easements (TCE) are anticipated in order to rebuild some entrances.  No permanent acquisitions are expected for this project. 

Who to Contact?

Contact Photo
Alvin's Portrait
Alvin Nieves-Rosario, P.E.
Title
Transportation Project Manager