Cole County - U.S. Route 54/Hickory Hill/Penny Hollow Intersection Improvements

Project Details:

The project is expected to take place in 2023.

Cost: 
The estimated project cost is
$2.923 million.

Work Taking Place
The project primarily includes the installation of J-Turn intersections
 at the Penny Hollow and Hickory Hill intersections on U.S. Route 54.

Learn more about J-Turns and how they can improve safety! 



Why is This Work Taking Place
Due to crash frequency and severity, the intersections at Hickory Hill and Penny Hollow were identified as the next highest priority following the initial round of improvements which is currently being constructed in Miller County. 


Traffic Impact: 
The work will require lane closures on U.S. Route 54 at various times throughout the project. MoDOT will alert the public of lane and road closures with updates through signs, news releases and social media. 

Counties Impacted
Cole
Project Status
Planning Phase
Route Impacted
U.S. Route 54

Project Highlights

In Progress
Public Comment Period
May 4-20, 2022
Not Started
Contract Award
Fall 2022
Not Started
Construction Begins
2023