Counties Impacted
Butler
Route Impacted
51
Work Type
Bridge Replacement
Planning Phase

Project Summary

The project includes replacing the Route 51 bridge over the St. Francis River at Fisk, Missouri in Butler County. This aging structure with a new, wider bridge. The current bridge is 21 feet wide, and the new bridge will be 36 feet wide.

During construction, Route 51 will be closed in the vicinity of the bridge with traffic detouring to use Route DD in Fisk. The Fisk St. Francis River access will remain open, but boat traffic will not be able to travel south during construction.

Tentatively, the project is expected to be let in November 2026. Construction could start as early as the beginning of 2027. Completion is anticipated approximately nine months after the start of construction.

Project Timeline

Public Meeting
Tuesday, Oct. 28 from 4 to 6 p.m. at the Fisk Community Center
milestone_icon
Tentative Letting
November 2026
milestone_icon
Construction Begins
As early as the beginning of 2027
milestone_icon
Anticipated Completion
9 months following the start of construction
milestone_icon
Image
Detour Map for Route 51 bridge closure over St. Francis River in Fisk MO

Meeting Handout

MoDOT held a public meeting from 4 to 6 p.m. Tuesday, Oct. 28, 2025. The meeting was held at the Fisk Community Center. View the meeting handout to learn more about the project and the detour route. 

Learn More