Counties Impacted
Bollinger
Route Impacted
51
Work Type
Intersection Improvements
In Progress

About

The proposed project includes upgrading the existing Route 34/51 intersection to improve turning movements for tractor trailers and other larger vehicles. This will be accomplished by widening and increasing some of the radiuses at the existing intersection. The project also includes improvements to the pedestrian crossings and adding a section of sidewalk to connect to the existing pedestrian facility.

Construction Update

Traffic to Use Magnolia, Crown Streets in Marble Hill

SIKESTON-Work to improve the Route 34/51 intersection in Marble Hill, Missouri will begin the week of July 14, weather permitting. 

During the first phase of construction, motorists will utilize Magnolia Street and Crown Street to bypass the work zone.  

Weather permitting, work will take place Monday, July 14 through Saturday, Nov. 1.  

The project will include upgrading the existing Route 34/51 intersection to improve turning movements for tractor trailers and other large vehicles. This will be accomplished by widening and increasing some of the radiuses at the existing intersection.  

The work zone will be marked with signs. Motorists are urged to use extreme caution while traveling near the area. 

For additional information, please contact Resident Engineer Kevin Plott at (573) 225-8409 or MoDOT’s Customer Service Center toll-free at 1-888-ASK-MODOT. 

Public Meeting Held June 10, 2024

MoDOT held a public meeting from 5 to 7 p.m. Monday, June 10 to discuss plans to improve the south Route 34/51 intersection in Marble Hill, Missouri. If you missed the public meeting, the meeting handout is available below.

Image
Icon for 34/51 Marble Hill Handout

View the Meeting Handout

Learn more about the proposed project, traffic impacts and the project timeline by visiting the link below. 

Learn More

Project Timeline

Complete
Public Meeting

June 10, 2024

milestone_icon
Complete
Tentative Letting

Feb. 2025

milestone_icon
In Progress
Construction Begins
July 14 - Nov. 1, 2025, weather permitting
milestone_icon
Anticipated Completion

Nov. 2025

milestone_icon

Contact Us

Contact Photo
Tim Pickett
Tim Pickett
Title
District Design Engineer
Department
Southeast District
Contact Info

(573) 472-9003

Contact Photo
Chris Crocker
Chris Crocker
Title
Project Manager
Department
Southeast District
Contact Info

(573) 380-1658