Project Summary

MoDOT is implementing a project to address aging pavement and traffic signals, the lack of connectivity for pedestrians and all modes of transportation, and drainage improvements on Route D (Page Ave.)  from east of Pennsylvania Avenue to the St. Louis City limits.  The project will study needs of this specific segment, including a possible road diet.  MoDOT will perform a Road Safety Audit (RSA) and will be soliciting feedback from the public in several ways throughout the project.

 PRINTABLE FACT SHEET

Project Milestones

Complete
Data Collection/Traffic & Safety Study
Fall 2023
milestone_icon
Complete
Stakeholder Survey
December 6, 2023 - January 3, 2024
milestone_icon
Complete
Public Meeting
December 13, 2023
4-6 p.m.
Midwest BankCentre, 6801 Page Ave. 63133

Below are meeting slides.  

 

milestone_icon
Complete
Conceptual Design
February 2024
milestone_icon
Complete
Public Meeting #2
Wednesday, September 18, 2024
4-6 p.m.
Carter Commons Food Hall Event Space
6746 Page Ave. 63133

This was a combined open-house style meeting with St. Louis County and their Pennsylvania Avenue Improvement Project.  Preliminary designs were shared. You may view the designs below.

PRINTABLE FACT SHEET

ROAD SAFETY AUDIT RESULTS SUMMARY

milestone_icon
Not Started
Final Design Plans
February 2025
milestone_icon

 

What improvements will be made?

  • Pavement resurfacing and new pavement markings.
  • Upgraded sidewalks to meet ADA requirements.
  • Additional sidewalks along the corridor to accommodate pedestrians.
  • Upgraded traffic signals at intersections to meet ADA standards from Pennsylvania to Skinker/Kienlen.
  • Drainage system improvements.

What will be the impact to traffic?

Right now, MoDOT is still studying the corridor.  Once construction begins (anticipated 2025), every reasonable effort will be made to reduce delays due to construction.  However, motorists using the route can anticipate daily lane closures and some night operations.

How much will the project cost?

This project construction amount is estimated at $12.5 million.

 

 

 

 

 

These slides, that include preliminary designs, were shared with attendees during the Route D public meeting on Sept. 28, 2024.  If you weren't able to attend the meeting, please review for additional information.  

 

 

 

 

 

These slides were available to attendees during the Route D public meeting on Dec. 13, 2023.  If you weren't able to attend the meeting, please review for additional information.  To view the complete slide, click on the link at the bottom of each. 

WHO TO CONTACT

Contact Photo
Photo of Tabitha Locke
Tabitha Locke
Title
Area Engineer, North St. Louis County
Department
St. Louis District
Contact Info

Office:  (314) 453-1749
Email:  Tabitha.Locke@modot.mo.gov

Contact Photo
Headshot of Jamie Rana, Transportation Project Manager in the MoDOT St. Louis District
Jamie Rana
Title
Transportation Project Manager
Department
St. Louis District
Contact Info

Phone: 314-624-5035
Email:  Jamie.Rana@modot.mo.gov