Counties Impacted
St. Louis
Route Impacted
D
Work Type
Bridge Replacement

Project Summary

The Missouri Department of Transportation (MoDOT) will be replacing the Route D/Page Ave. bridges over Route 67/Lindbergh Blvd. as they have reached the end of their useful life.

The new bridges will be built to meet required vertical clearance. Connecting pavement and existing loop ramp pavement will be repaved.  Horizontal alignments will be adjusted on the loop ramps to meet standards.  Drainage, guardrail, signage and lighting upgrades are included in the project.

Project Milestones

Complete
Final Plans
December 2024
milestone_icon
Complete
Virtual Stakeholders Meeting
February 19, 2025, 10 a.m.

Click HERE to view presentation.

milestone_icon
Complete
Project Letting
March 2025
milestone_icon
Complete
Contract Awarded
April 2025
milestone_icon
Construction Begins
May 5, 2025
milestone_icon
Project Completed
November 2026
milestone_icon

What is the Average Daily Traffic (ADT) along the corridor?

An averge of 39,000 motorists use the the corridor on a daily basis.

Will there be any right of way acquisitions?

No, there will not be any right of way acquisitions.

What is the cost of constructing the new bridges?

The construction cost is $10.5 million.

When will construction begin?

Construction is anticipated to begin summer 2025.

Embed
Route D Project Area
Is Responsive
Embed Code

Who to Contact

Contact Photo
Photo of Tabitha Locke
Tabitha Locke
Title
Area Engineer, North St. Louis County
Department
St. Louis District
Contact Info

Office:  (314) 453-1749
Email:  Tabitha.Locke@modot.mo.gov

Contact Photo
Headshot of Jamie Rana, Transportation Project Manager in the MoDOT St. Louis District
Jamie Rana
Title
Transportation Project Manager
Department
St. Louis District
Contact Info

Phone: 314-624-5035
Email:  Jamie.Rana@modot.mo.gov