Project Summary
The Missouri Department of Transportation (MoDOT), working with its consultant Wilson & Company, is preparing for a bridge improvement project on Missouri Route 22 in Audrain and Boone counties 0.2 mile west of Missouri Route 151 west junction near Sturgeon. Improvements include the realignment of the corridor at this location with a new bridge consisting of 12’ lanes with 4’ shoulders. An environmental evaluation will be conducted to determine a viable design solution for this area.
Project Milestones
November 12, 2024
Spring 2025 through 2026
Winter 2026-2027
Spring 2027
Contractor: TBD
Contract Amt: TBD
Summer 2027
Winter 2027

Project Information and Public Engagement
Public Informational Meeting - November 12, 2024 | 3:30 - 5:30 p.m.
Location: Multipurpose Room – Sunnydale Seventh-day Adventist Church, 6964 Audrain Road 9137, Centralia, MO 65240
- Project Handout
- Online Comment Form (see below)
- Available November 12 at 3:30 p.m. to November 26 at 11:59 p.m.
News Releases
-
Public Meeting To Be Held for Missouri Route 22 Bridge Replacement Near Sturgeon
HANNIBAL – Individuals are invited to a public informational meeting that will share information about the future bridge replacement project on Missouri Route 22 in Audrain and Boone counties. The bridge over Canadian Pacific Kansas City Southern...
Project Media
Frequently Asked Questions
How much does the project cost?
Approximately $8-10 million
What are the anticipated impacts?
Construction details have not been finalized at this time. MoDOT will work with residents and business owners to ensure access is available during construction.
Will the road be closed during construction?
Most construction activities will take place on new alignment away from Route 22. Short-term closures may be necessary to tie Route 22 and Route 151 into the new roadway. More information regarding traffic impacts will be shared through news releases and social media for each stage of construction as details become available.
Will MoDOT need to acquire any right of way?
Yes. In 2025, MoDOT's Right of Way staff and consultants will begin the process of contacting property owners for any necessary right of way needed for the project. Right of way discussions are anticipated to continue through 2026.
How can I stay updated about the project?
Stay updated on news about roadwork in your area by signing up for emails at eUpdates at MoDOT.org
Who can I contact if I have further questions?
Questions about the project may be directed to Keith Killen, MoDOT's project manager overseeing the project at keith.killen@modot.mo.gov or Emily Edgar, Area Engineer, at emily.edgar@modot.mo.gov
Project Contacts

Keith Killen, P.E.
Title
Project Manager
Department
Northeast District
Contact Info