Improve I-70 KC History

Background

A National Environmental Policy Act (NEPA) re-evaluation was necessary because the Final EIS document was last updated approximately five years ago, and the existing conditions, possible solutions, potential impacts, and related mitigation measures may have changed. Several bridges, as well as pavement along this corridor, have been repaired many times, but now must be replaced to meet the demands of the 21st century. While this work is underway, it is the perfect opportunity to improve connectivity between the neighborhoods.

What is an Environmental Study Re-Evaluation?

An environmental study re-evaluation is a process to review the environmental impact categories and commitments to ensure that any recent changes to the corridor are incorporated into the document.

During the current phase of work these are the primary goals:

  • Re-evaluate potential impacts of the previously determined preferred alternative, current conditions and related mitigation measures that may have changed.
  • Engage with stakeholders to provide a project status and update previous feedback.
  • Prepare the project to move forward into design.

Previous Studies

Complete
2000
I-70 Major Investment Study

In August 2000, MoDOT, the Mid-America Regional Council, and the Kansas City Area Transportation Authority started a Major Investment Study (MIS) for the I-70 corridor in Jackson County.

The study area spanned approximately 28 miles from Kansas City Missouri’s Central Business District (CBD) Freeway Loop to the State Routes F/H interchange in Oak Grove, Missouri.

The objective of the I-70 MIS was to identify a multimodal investment strategy to address transportation needs in a manner consistent with regional policy goals. The I-70 MIS concluded in November 2004, and it identified a package of recommendations that included the reconstruction and widening of the existing I-70 facility.

milestone_icon
Complete
2008
I-70 First Tier Environmental Impact Statement

In July 2008, MoDOT in partnership with the Federal Highway Administration initiated the I-70 First Tier Environmental Impact Statement (EIS) process for approximately 18 miles of I-70 corridor from the end of the last ramp termini east of the Missouri and Kansas state line to east of the I-470 interchange, including the entire Kansas City, Missouri’s Downtown Central Business District (CBD) Freeway Loop.

Its purpose was to determine an improvement strategy for the corridor to address the following needs - improve safety, reduce congestion, restore and maintain existing infrastructure, improve accessibility, and improve goods movement.

Various concepts were combined to develop 15 initial strategies that were screened down to four first tier strategies.

These four strategies included the No-Build Strategy, Improve Key Bottlenecks Strategy, Add General Lanes Strategy, and Transportation Improvement Corridor Strategy.

After analysis and public review, the First Tier EIS identified a Selected Strategy to improve the I-70 corridor.

The Selected Strategy is the Improve Key Bottlenecks Strategy from the downtown loop to east of I-435. From east of I-435 to I-470, the Selected Strategy is either the Improve Key Bottlenecks Strategy or the Add General Lanes Strategy. The I-70 First Tier EIS concluded with a Record of Decision in April 2011. The First Tier EIS recommended that for the second tier environmental studies, the 18-mile I-70 corridor be divided into five sections of independent utility (SIU).

The intent of the second-tier environmental studies is to build on and extend the work of the First Tier EIS for improving I-70 as part of the Mid-America Regional Council’s long-range transportation plan.

Each SIU will be evaluated to the appropriate level of detail (CE, EA, or EIS) within the National Environmental Policy Act process.

 

milestone_icon
Complete
2009
I-70 Statewide Environmental Study

In August 2009, MoDOT in partnership with the Federal Highway Administration completed a Supplemental Environmental Impact Statement across the state incorporating truck-only lanes on I-70 between Kansas City and St. Louis. The study area included 9 miles of I-70 in Jackson County from east of the I-470 interchange to the State Routes F/H interchange in Oak Grove.

 

milestone_icon
Complete
2011
I-70 Second Tier Environmental Impact Statement

In December 2011, the Missouri Department of Transportation (MoDOT) and the Federal Highway Administration completed a Second Tier Environmental Impact Statement (EIS) for approximately 6.8 miles of I-70 from west of the Paseo Boulevard interchange to east of the Blue Ridge Cutoff interchange. This study encompassed two sections of independent utility (SIU) from the I-70 First Tier EIS, which are the Urban SIU (Paseo Boulevard to U.S. 40) and I-435 Interchange SIU (U.S. 40 to Blue Ridge Cutoff). The Second Tier EIS carried forward and refined the needs identified from the First Tier EIS and conduct an alternatives analysis based on the Improve Key Bottlenecks Strategy.

Through this study, more specific definitions of the improvements and their potential impacts were developed for consideration by the general public and the various environmental and community resource agencies. Examples of these improvements include modifying access, fixing existing pavement and bridges, improving interchange ramps, adding collector distributor roads, and providing for bus transit on shoulder. The Second Tier EIS also evaluated a no-build alternative and alternatives coordinated with ongoing regional transit studies.

This study lasted about 30 months and concluded in spring 2014.

milestone_icon
Complete
2017
Project Development Suspended

Due to budget constraints, MoDOT suspended the project development process for improvements between January 2015 and June 2016. In 2017, MoDOT reactivated the environmental review process and began to finalize the draft EIS in order to move the project forward. 

 

milestone_icon
Embed
KC I-70 Environmental Impact Studies Map
Summary

Map Instructions: Click the menu button located on the upper left hand corner of the map (it is a black and white button with an arrow located to the left of the MoDOT logo) to select which map you'd like to view. You can view the current I-70 corridor study, the Second Tier I-70 EIS area, and the First Tier I-70 EIS area. 

Is Responsive
Embed Code