Counties Impacted
Howard
In Progress

Howard County - Route 40 Salt Creek Bridge Replacement

Below are details, resources and news about the replacement of the 80-year-old Howard County Route 40 Bridge over Salt Creek and the Katy Trail. The bridge has reached a point where replacement is necessary. The Route 40 bridge is included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state.



Project Details

When: 

The project is underway.

Work Taking Place

Crews will replace the bridge and widen it by two feet, increasing motorists' safety.

Traffic Impact: 

The bridge is closed during replacement.  

Project Milestones

Complete
Public Comment Period
March 10 - 24, 2021
milestone_icon
Complete
Bid Awarded
January 5, 2022

The Missouri Highways and Transportation Commission awarded the contract to Lehman Construction, which provided a low bid of $6,952,040. This contract also includes the bridge deck replacement on Route 40 over Bonne Femme Creek , and the replacement of the Cooper County Route F bridge over Stephens Branch.  

milestone_icon
Complete
Work Begins
June 6, 2022

The bridge is closed during replacement. 

 

milestone_icon
Complete
Project Completion
March 14, 2023
milestone_icon

Project News & Updates

Image
CD Social Media Icons

Stay Connected!

Check out facebook.com/modotcentral and @MODOT_Central on Twitter to follow us and know what's happening near you! You can also click the button below to subscribe to district news and have the information sent straight to your inbox! 