What is this project?

This project will make crossroad, interchange and outer road improvements to I-70 in St. Charles County, between Fairgrounds and Cave Springs Roads, to make the corridor safer and more efficient. For more information, contact Project Director Stacey Smith at 314-453-5084 or by email at anastasia.smith@modot.mo.gov

 

PROJECT GOALS:

  1. Maximize improvements within the program budget of $62 million.
  2. Improve safety and efficiency of the transportation network while supporting connectivity for the local community.
  3. Provide a durable and maintainable transportation infrastructure allowing for future expansion.
  4. Minimize impacts to the traveling public during construction while safely delivering the project by November 1, 2023.
  5. Deliver the project using a diverse workforce.

 

Counties Impacted
St. Charles
St. Louis
Project Status
Planning Phase

Project Timeline

Not Started
Letters of Interest Due

TBD

Not Started
Project Advertisement

November 2, 2020 

Not Started
Industry Meeting/ RFQ Release

December 7, 2020

Not Started
SOQ Shortlist

January 18, 2021

Not Started
RFP Released

February 5, 2021

Not Started
Proposals Due

TBD

Not Started
Award at MHTC Meeting

June 2021

Not Started
Construction Begins

TBD

Not Started
Construction Complete

TBD