Counties Impacted
McDonald
Completed

Project Details: Route KK/Pine Creek Bridge

  • Replace bridge over Pine Creek
  • New bridge will be six feet wider, three feet longer than existing
  • Guardrail will be added to ends of the bridge
  • Approximately 274 vehicles per day use the bridge
  • Current bridge was built in 1962

Project Details: Route U/Star Hollow Bridge

  • Replace bridge deck (driving surface) with a new surface
  • Bridge deck will be widened by two feet
  • Guardrail will be added to ends of the bridge
  • Approximately 180 vehicles per day use the bridge
  • Current bridge was built in 1960

Construction: 2019

Proposed Traffic Impacts:

  • Drivers will need to find alternate routes during the work
  • No signed detours are planed
  • Drivers will have access to entrances at either end of the work zones, but will not be able to drive through them

Estimated Total Project Cost:

       Route KK/Pine Creek Bridge: $830,000

       Route U/Star Hollow Creek Bridge: $497,000

Project Updates

  • McDonald County Route KK Bridge Over Pine Creek

    08/26/2019

    McDonald County –McDonald County Route KK bridge over Pine Creek east of Jane will be CLOSED for up to 100 days while the old bridge is replaced with a new one starting the week of September 3, the Missouri Department of Transportation said.

    Contrac...

  • McDonald Co. Route U Bridge Over Star Hollow Creek

    07/10/2019

    McDonald County –McDonald County Route U bridge over Star Hollow Creek south of Rocky Comfort will be CLOSED for up to 95 days to have its driving surface replaced starting the week of July 15, the Missouri Department of Transportation said.

    Contrac...