Counties Impacted
Chariton
Route Impacted
24
Completed

Project Timeline

Complete
Design Phase

MoDOT designed new structures to replace the bridges over the Middle Fork Chariton River and Middle Fork Chariton River Overflow.

milestone_icon
Complete
Contractors Bid on Project

This project was a part of MoDOT's June 2019 letting, when contractors may submitted competitive bids for the project.

milestone_icon
Complete
Contract Awarded

The Missouri Highways and Transportation Commission awarded a $4,269,513.15 contract to E & C Bridge, LLC at their July 2019 meeting.

milestone_icon
Complete
Contractor Begins Work

The contractor began work in August 2019.

milestone_icon
Complete
Completion Date

The contract completion date is currently set for December 2020. The contractor was able to fully open both bridges to all traffic in March 25, 2020.

milestone_icon
Image
Middle Fork Chariton River Bridge

Current Middle Fork Chariton River and Overflow Bridges

  • Both built in 1946 - The Middle Fork Chariton River Overflow Bridge was rehabbed in 1946
  • Does not meet current standards
  • Both have a width of 26 feet (two 12-foot lanes)
  • Both have one-inch shoulders
Image
Middle Fork Chariton River Overflow Bridge

New Middle Fork Chariton River and Overflow Bridges

  • Will meet current standards
  • Will remain along same alignments as previous bridges
  • Both will have a width of 44 feet (two 12-foot lanes)
  • Both will have 10-foot shoulders

Frequently Asked Questions

 

Q: Will MoDOT close the bridges during construction?

A. No, one lane will remain open throughout the project. Motorists will be guided through the work zone by traffic signals and barriers.

 

Q: How long will the road remain closed?

A.  The exact length of the closure has not been determined.

 

Q. Will you have to acquire any right of way?

A. Right of way is not needed for this project.

 

Q: Who can I contact if I have further questions?

A. Questions about the project may be directed to MoDOT Customer Service at nwcr@modot.mo.gov or by calling 888 ASK MODOT (1-888-275-6636Image removed.Image removed.Image removed.Image removed.)

 

Q: How can I stay updated on the project's progress?

A. Sign up for project-specific updates using the form below.

Middle Fork Chariton River and Overflow Bridge News

For more information about this or other MoDOT projects, please contact our 24-hour Customer Service line at 888 ASK MODOT (1-888-275-6636).