Route 364 (Page Extension)

Phase 3 logoRoute 364 Page Ave Phase 3

MoDOT, St. Charles County and the local muncipalities have teamed together to allocate $118.2 million towards building Route 364 Page Phase 3.  The $118.2 million will be used for purchasing property, utility relocations, design and construction.  The project includes building an improved connection from Page Phase 2 at Route 94 and Mid Rivers Mall Drive to I-64/US Route 40/61 at Route N.

MoDOT used a Design-Build contracting process to have contractor teams compete to win the contract. The Missouri Highways and Transportation Commission approved the contract February 6, 2013, awarding the project to the Page Constructors Joint Venture, including Fred Weber Inc., Millstone-Bangert Inc., Kolb Grading with lead designer Parsons Transportation Group.

Click here for information on the Design-Build Contractor

Route 364 map from I-64 to Route 94

What will be built?

Page Constructors is designing and building a four lane divided freeway for nine miles from Route 94 at Mid Rivers Mall Drive in St Peters to Interstate 64 in Lake Saint Louis.  The new highway will include the following details:

  • additional ramps connecting Route 94 and Mid Rivers Mall Drive to Route 364

  • bridge over Motherhead Road

  • Gutermuth Road bridge over Route 364

  • Single Point interchange at Route K with widening Route K to six lanes north and south of the interchange

  • Folded diamond at Bryan Road with north outer road extended from Stump Road to Bryan Road

  • bridge over Hanley Road

  • bridge over Henke Road with ramps to and from the east

  • new ramps to complete the cloverleaf interchange at I-64

Map of Route 364 Phase 3

Corridor map showing new road and interchanges (pdf)

See public meeting displays below for more maps.

Schedule for construction of Route 364 Phase 3

Route 364 Phase 3 will have construction start in May 2013. There will be construction activity along all nine miles of the project until the new road opens in sections in the fall of 2014.  I-64 to Bryan Road will open end of August 2014.  Bryan Road to Route K will open in early October 2014.  Route K to Route 94 will open at the end of October 2014.  The entire project will be complete by late November 2014.

Schedule map (pdf)

Public Displays and Maps

A public meeting was held Tuesday, March 26 at the St. Charles Community College. All of the material presented is available here.

All files are pdfs.

Nine-mile corridor map from Route 94 to I-64 (601 Kb)

Nine-mile corridor map shown with profile grade of new road

(NOTE: The scale shown on the corridor map is based on the 8 foot long display at the public meeting. it will not be to scale when you view this online or print it out.)

All information displays and interchanges in one file (7.3 Mb)

Welcome_Goals_Stay Informed (344 Kb)

Construction Schedule (170 Kb)

Completion Schedule (2.2 Mb)

General Project information (866 Kb)

I-64 interchange (1.5 Mb)

Henke Road interchange (492 Kb)

Bryan Road interchange (466 Kb)

Route K interchange (867 Kb)

Gutermuth and Motherhead roads (475 Kb)

Route 94/Mid Rivers Mall Drive interchange (589 Kb)

 

Construction Traffic Impacts

Gutermuth Road at Old Gutermuth Road closed May 29-August 30, 2013

Map of the detour on Old Gutermuth Road (pdf)

Photo Library

Route 364 Page Phase 3 Groundbreaking

Route 364 Page Phase 3 Groundbreaking May 22, 2013.  To see more photos, check them out on Flickr by Clicking Here.

Barrel Bob at Route 364 Groundbreaking

Barrel Bob at the Groundbreaking Ceremony

 

 

Construction Photos To Come Here Soon

Environmental Impact Statement Documents

Route 364 History

Click here for information on sections of Route 364 already complete from I-270 in St Louis County to Mid Rivers Mall Drive in St Peters.

For more information

For more information on Phase 3 of the Route 364 upgrade, contact Project Director Mike Castro at 314-275-1500 or 1-888-ASK-MoDOT (275-6636) or by Route.364@modot.mo.gov.

To sign up for email updates, please contact Community Relations Coordinator Linda Wilson Horn at Linda.wilsonhorn@modot.mo.gov.

 

 

 

 

 

 

 

 

 

 

 
District Map
St. Louis District
spacer
Traveler Information
Traveler Map
Gateway Guide
Around St. Louis 511
map
call, cell, mobile, phone iconText Alerts - Sign Up!
spacer
Quick Links
Your Local Area Engineer
Report A Road Concern
Blanchette Bridge
Mississippi River Bridge
Route 364
Daniel Boone Bridge
On the Move
spacer
Your Local MoDOT
Get your local district information.
Districts Map
Northwest Northeast Kansas City Central St. Louis Southwest Southeast
About Us
How Do I...
Contact Us
Missouri Department of Transportation
Central Office
105 W. Capitol Avenue
Jefferson City, MO 65102
1-888-ASK-MODOT (275-6636)
horz_bar
| | |
Missouri State Government
 
© 2013 Missouri Department of Transportation. All Rights Reserved.   Privacy Policy.
 
 
Facebook Twitter Flickr Blog YouTube Franklin Jefferson St. Charles St. Louis St. Louis City Northwest Northeast Kansas City Central St. Louis Southwest Southeast iTunes Android