There are many drainage pipes and box culverts along Route P between 50 and 60 years old that need to be replaced.
What Is The Proposed Solution for Improvements Along Route P?
MoDOT will replace approximately 25 aging drainage pipes and box culverts along Route P between Route A and Route 110.
How Will Traffic Be Impacted While Construction Is Under Way?
Short-term daily road closures may be necessary while crews replace the drainage pipes and box culverts along Route P.
Estimated Project Cost:
Approximately $1 million is budgeted for construction of this project.
View photos of the existing box culverts to be replaced with this project:
Culvert1 Photo Culvert2 Photo
Culvert3 Photo
Culvert4 Photo Current Project Timeline: September 18, 2007 Hold informational public meeting. January 2009 Final design will be complete. April 2009 This project is expected to be awarded to a contractor. May 2009 Construction begins. Fall 2009 Construction complete.
Who Do I Contact For More Information?
On the web: www.modot.org
Check Your Route for Work Zones
Weather-Related Road Conditions Map
Potholes Mowing Traffic Signals & Signs
Job Listings and Applications