Route 100 Widening Project


MoDOT and City of Washington Officials with Ceremonial $20 million dollar bill

MoDOT, Missouri Highways and Transportation Commission, the City of Washington take part in a groundbreaking ceremony Friday, June 6, to kick off construction of the Route 100 widening improvement project. MoDOT and the City of Washington are partnering in this $ 21.1 million dollar cost-share project.

The partnership between MoDOT and the City of Washington is monumental for the economic growth in the St. Louis region, City of Washington and surrounding areas. The widening of Route 100 will improve the capacity and safety of the highway for Franklin County motorists.

 

View the Project Maps:


The documents are provided in Acrobat Reader format. Free Acrobat Reader download PDF Icon



Why Does Route 100 from Interstate 44 to Route 47 Need Improvements?

The Route 100 Widening Project is a cost-share partnership between MoDOT and the City of Washington, which has been awarded to Millstone Bangert for approximately $21.1 million. Route 100 from Interstate 44 to Route 47 has exceeded its capacity for a two-lane roadway and can no longer handle the amount of traffic that uses it on a daily basis. MoDOT has identified traffic congestion and safety as the major transportation issues of concern. In 1972, Route 100 between Interstate 44 and Route 47 was rebuilt to provide a straighter alignment and improve visibility at intersections. In 2003, the roadway was resurfaced. The current average daily traffic count is 16,000 vehicles per day. By 2020, that volume is expected to nearly double to 30,000 vehicles per day.

                                                 


What Improvement Along Route 100 are Being Proposed?

  • Based on the evaluations in the August 2004 final environmental assessment, which is a planning and environmental study used to determine a preferred alternative for the roadway, MoDOT recommends the construction of two additional lanes north of the existing two-lane roadway.
  • Route 100 from Interstate 44 to west of Ranch Bluff Road will be widened to two lanes in each direction with a continuous center-turn lane. The continuous center-turn lane is necessary because of the need for left-turn movements. This will be built to the north of the existing roadway.
  • Route 100 from west of Ranch Bluff Road to west of St. John’s Road will be a four-lane divided highway with a 42-foot grass median. This will be built to the north of the existing roadway. There isn't as much of a need for left-turn movements, so the access points are controlled to improve safety on this stretch of roadway. Median crossovers, where motorists can make left turns via deceleration lanes on the four-lane divided highway, will be provided to existing side streets.
  • Route 100 from west of St. John’s Road to Route 47 will be widened to two lanes in each direction with a continuous center-turn lane. The continuous center-turn lane is necessary because of the need for
    left-turn movements. Two lanes will be added to the north of the existing roadway, and one lane will be added to the south of the existing roadway. The existing signalized intersections will remain signalized.
  • The bridge at Dubois Creek will be widened, and the bridge deck will be replaced. A new AmerenUE Railroad Bridge will be constructed parallel to the existing bridge on the north side.


How Will Traffic Be Impacted During Construction?

  • Temporary lane closures and temporary bypasses will be used during construction to ensure traffic flow through the work zone. Construction is expected to be complete in June 2010.


Current Project Timeline

May 9, 2006

Held informational open house meeting.

Fall 2006

Right of Way plans were completed.

Early 2007
Right of Way negotiations began.

February 2008

Final design was completed.

March 2008

Contractors bid on the project.

April 2008

The project was awarded to a contractor.

June 2008

Construction begins.

June 2010

Construction will be complete.


Who Do I Contact For More Information?

  • Contact MoDOT Community Relations Specialist Kara Price at 1-888 ASK MODOT (275-6636) or email  Kara.Price@modot.mo.gov.
   
   
TRAFFIC CONTACT CONTACT SURVEY SURVEY CAREERS CAREERS NEWS NEWS SITEMAP SITEMAP TRAFFIC Kansas City Area Southwest District North Central District Central District Springfield Area Northeast District St. Louis Area South Central District Southeast District Northwest District