| |
St. Louis District Facebook Twitter Flickr Blog YouTube RSS

Interstate 64 Double Deck Rehabilitation Work      



I-64 Double Deck Interstate Section


What is the latest on this project?

Work continues on this project through the end of 2012. MoDOT is working with the various downtown attractions (Busch Stadium, Peabody, Edward Jones Dome, ScottTrade, etc.) to ensure traffic can get through for events. Driver can still expect morning lane closures on eastbound I-64 for safety.

Project News Release

Tips to navigate through lane closures on I-64 downtown

Best and worst times to travel through downtown project (May 22)

MoDOT updates schedule for I-64 double deck work downtown (October 3)

Work continues on the westbound bridge's driving surface. Even though barrier is removed from the roadway, MoDOT still closes up to two lanes during non-peak traffic (morning rush) on westbound I-64. All lanes on westbound I-64 at the double deck are open between 5 a.m. and 10 a.m. weekdays.

Work on westbound I-64 required a number of full weekend closures of the westbound interstate to complete. Westbound weekend closures are currently complete.

Work has begun on eastbound I-64 and continues through the remainder of the year. For safety, both the Forest Park and the Pine Street ramps to eastbound I-64 will be closed until mid-December. Up to two lanes may be closed on eastbound I-64 during non-peak traffic (evening rush).  All lanes on eastbound I-64 are open between 2 p.m. and 8 pm. weekdays.

Currently, the schedule calls for the following weekend closures of I-64.  All weekend full closures of the interstate have been completed.

Westbound I-64

  • June 1-3 (completed)
  • June 22-24 (completed)
  • July 13-15 (completed)
  • July 27-29 (canceled - to be rescheduled)
  • August 10-12 (completed)
  • August 24-26 (completed)
  • September 14-16 (completed)
  • September 21-24 (completed)

Eastbound I-64

  • October 5-8 (completed)
  • October 19-21(postponed)
  • November 3-5 (completed)
  • November 10-12 (completed)
  • November 16-19 (completed)

Why are Improvements Needed on I-64's Double Deck Bridge from 21st Street to the Poplar Street Bridge?

The I-64 double deck approach to the Poplar Street Bridge extends from 21st Street to the bridge. This structure is in a double deck configuration from approximately 14th Street to Broadway. The bridge was opened to traffic in November 1967 and is over 43 years old. The double deck needs to be rehabilitated to ensure a longer lifespan. The expansion joints in between the bridge decks also need to be replaced because they are in poor condition due to age.


Below are links to photos of the current driving surface of the I-64 double deck bridge:

Underside of the double deck bridge

Side of the double deck bridge

Driving surface of the double deck bridge

Expansion joint on the double deck bridge


What Improvements Will MoDOT Accomplish?

  • Repair the driving surface lanes and put a new concrete surface on it to gain a longer year lifespan up to approximately 25 years.
  • Replace 37 expansion joints.
  • Repair remaining drainage structures on and below the bridge decks.


Aerial View of the Project Limits


How Will Traffic Be Impacted?


Traffic will be impacted by various lane closures on weekdays and weekends while crews repair the I-64 double deck bridge. Interstate 64 will be fully closed for several weekends while the work is occurring between 21st Street and the Poplar Street Bridge.



Detour Routes

 

Motorists can use I-70 and I-55/I-44 as alternate routes to and from downtown St. Louis. Motorists can also use Jefferson Barracks Bridge and Chain of Rocks Bridge, along with other bridge crossings in the downtown area, such as the Martin Luther King, Eads and McKinley bridges.


St. Louis Regional Detour Map

Local Detour Map for Eastbound I-64 closure

Local Detour Map for Westbound I-64 closure


How Can You Help?

  • Use alternate routes for your commute.
  • Adjust your travel times.
  • Shift your work hours.
  • Use Metrolink or Metrobus.
  • Telecommute if possible.
  • Visit www.modot.org/stlouis for construction updates.

                                                      

I-64 Corridor in Downtown St. Louis

I-64 General Construction Information Overview



Who Do I Contact For More Information?

  • Contact MoDOT Community Relations Specialist Andrew Gates at 1-888 ASK MODOT (275-6636) or email Andrew.Gates@modot.mo.gov


 
District Map
St. Louis District
spacer
Traveler Information
Traveler Map
Gateway Guide
Around St. Louis 511
map
call, cell, mobile, phone iconText Alerts - Sign Up!
spacer
Quick Links
Your Local Area Engineer
Report A Road Concern
Blanchette Bridge
Mississippi River Bridge
Route 364
Daniel Boone Bridge
On the Move
spacer
Your Local MoDOT
Get your local district information.
Districts Map
Northwest Northeast Kansas City Central St. Louis Southwest Southeast
About Us
How Do I...
Contact Us
Missouri Department of Transportation
Central Office
105 W. Capitol Avenue
Jefferson City, MO 65102
1-888-ASK-MODOT (275-6636)
horz_bar
| | |
Missouri State Government
 
© 2013 Missouri Department of Transportation. All Rights Reserved.   Privacy Policy.
 
 
Facebook Twitter Flickr Blog YouTube Franklin Jefferson St. Charles St. Louis St. Louis City Northwest Northeast Kansas City Central St. Louis Southwest Southeast iTunes Android