UPDATE: Rock blasting work will begin April 11 at 1 p.m., along southbound Interstate 270 between Manchester and I-44. All lanes on both directions of I-270 in this section will be closed for up to 15 minutes on weekdays to blast rock as part of the widening construction. This blasting work and interstate closure is weather permitting.
MoDOT has enhanced work zone warning signs to make them more visible to motorists so they know about the interstate closures. Check out our online Traveler Information Map with work zone information to help you plan your trip during these daily closures.

Northbound I-270 now has an extra lane between I-44 and Manchester Road
What is the problem?
The stretch of Interstate 270 between Interstate 44 and I-64 is one of the most heavily traveled sections of interstate in the St. Louis greater metropolitan area. On average, between 175,000 and 185,000 vehicles travel the section of interstate each day. During morning and evening rush periods, the heavy levels of traffic cause significant backup. In the morning, traffic on northbound I-270 backs up from about Big Bend to Gravois (Route 30). In the evening, it is not unusual to have traffic backups on southbound I-270 from Dougherty Ferry to Olive Boulevard (Route 340) or Page Avenue (Route 364). A significant amount of merging traffic from I-44, railroad bridges with columns just off the roadway and the rock bluffs on the east side of the roadway all contribute to overall congestion on the interstate.
During a typical weekday morning commute, traffic slows to 35 miles an hour in this stretch of northbound I-270. It takes about 10 minutes more to drive this stretch of roadway than when the roadway isn’t congested.
What options were looked at?
This particular stretch of northbound I-270 has a lot of areas which provide design concerns – among them, traffic ramps from Watson Road, eastbound and westbound I-44 and Big Bend; the rock bluffs on the east side of the interstate and a narrow railway bridge south of Dougherty Ferry. Southbound also has the narrow railroad bridge, the ramp to Big Bend, as well as ramps to eastbound and westbound I-44 and Watson Road.
What is the solution?
There is no easy solution to all of the problems, since there is so much traffic moving between so many different places. A portion of the solution involves increasing the merge lanes from Watson and eastbound and westbound I-44 onto northbound I-270 and adding one more through lane onto northbound I-270 between I-44 and Manchester Road. MoDOT is also adding an additional through lane on southbound I-270 between Dougherty Ferry and I-44. Because of the restrictions on the roadway, MoDOT will be widening the roadway somewhat, but will have to permanently narrow all lanes on northbound and southbound I-270 to 11 feet (the same width as I-44 during the I-64 reconstruction in 2009 and 2010). As much as possible, MoDOT will maintain full shoulders along the roadway.
MoDOT will narrow and shift the existing four lanes from Manchester to I-44 in the two year project, so motorists will have no shoulders in some locations as crews widen the road. There should be some lane closures at night as part of this work. When construction is completed, travel times through this corridor should decrease during peak hours and reduce traffic delays.
What will this solution require?
This work will require about two years of construction on I-270, to include widening work, roadway construction and work in the rock bluffs. We will narrow and shift the existing four lanes in that area early in the two year project, so drivers will have no shoulders in some locations as we widen the road. There should be minimal lane closures as a part of this work.
Construction overview northside of project (7.8 Mb)
Construction overview southside of project (8 Mb)
What will happen to the rock bluffs just north of I-44?
Some of the rock bluff will need to be removed as part of the widening project. The way that will be completed has not yet been determined.
Will sound walls be included?
**Six sound walls are being built for this project.
MoDOT has conducted a sound study for the corridor and determined which areas may qualify for a sound wall. Six sections of the roadway have qualified for sound walls and will be built in the following locations: (Click below to see the six qualified locations highlighted in yellow and blue).
Sound wall locations
The department has held several meetings with the affected residents to discuss the sound study and why they may or may not qualify for a sound wall. For more information on sound walls and sound wall criteria, please surf to this web page.
What is the timeline for work?
Construction for this entire project on I-270 will occur for approximately two years, which includes widening work, roadway construction, work in the rock bluffs and installing soundwalls. Construction of northbound widening work is now complete. The southbound work begins in 2013.
For more information, contact: