I-44 Gasconade River Bridge Rehabilitation:

 



 

New-to-Missouri Construction Technique Shortens
Closure of I-44/Gasconade River Bridge Near Lebanon

 

Time Lapse Video

 

Project:

The westbound lanes of I-44 at the Gasconade River east of Lebanon were opened to traffic Tuesday morning, May 24, after being closed for only 20 days instead of 60 days because of a new-to-Missouri "bridge jacking" construction technique. One westbound lane was opened on Monday, May 23.

A new 670-foot long bridge deck with underlying girders attached -- weighing 2,000 tons -- was built next to the existing bridge. Hydraulic jacks were used to slide the new superstructure into place in one piece during a 10-hour operation on one day.

The process, employed elsewhere in the United States and in other countries, will be used again in Missouri later this year -- in a project to rehabilitate a Route 5 bridge over the Lake of the Ozarks at Hurricane Deck north of Camdenton.

On May 5, the I-44 westbound lanes at the Gasconade River bridge were closed and westbound traffic was shifted to the eastbound side. That meant only one lane of traffic was open in each direction along a half-mile long stretch. Traffic was slowed.

However, by using this innovative method of bridge construction -- building the superstructure on temporary columns and "sliding" the new deck-and-girder assembly onto the existing bridge's columns-- only 20 days of "head-to-head" traffic were needed. Traditional reconstruction methods would have kept the westbound lanes closed for at least 60 days.

Shortening the time needed for such a traffic constriction reduced disruption and improved safety on busy I-44.

The I-44 westbound bridge over the Gasconade River was built in 1955. Its deck had deteriorated considerably and, in recent years, needed frequent repairs. The repair work often required day and night lane closings.

 

Heavy Lifting:

To tackle the bridge rehabilitation project and be in a position to earn incentive pay to complete the job and open the bridge ahead of schedule, construction contractor Emery Sapp and Sons of Columbia recruited Parsons Engineering of Denver, CO, to design a temporary substructure on which to build the new bridge deck and girders and to plan the move of the new superstructure onto the existing columns.

Emery Sapp brought in another subcontractor to do the actual "bridge jacking" work. The company is Mammoet, a privately-held Dutch company specializing in the hoisting and transporting of heavy objects. (Mammoet is Dutch for mammoth.) The Mammoet crew came out of Houston, TX.

To put the problem of moving a 2,000-ton mass into perspective:

* The Lebanon Fire Department's Ladder No. 1, its largest piece of firefighting equipment, weighs 40 tons. The bridge's new superstructure is equal to 50 Ladder No. 1s.

* At Springfield's Dickerson Park Zoo, bull elephant Mr. Ed weighs 6 tons. It would take 333 Mr. Eds to equal the weight of the bridge's new superstructure.

In the end, using the "bridge jacking" technique, Emery Sapp earned an extra $600,000 in incentives by completing the project and getting the westbound lanes open quickly ($40,000 a day, capped at 15 days). Emery Sapp also earned an extra $600,000 in incentives for early completion of the resurfacing of a nine-mile section of westbound I-44 at St. Robert. Total cost of the project at St. Robert and the Gasconade River came to $12.2 million.

 

Here's an abbreviated description of the bridge rehabilitation and "bridge jacking" process:

  • In mid-February, construction began on temporary bridge columns on the north side of the westbound bridge. Four new girders, with longest span length of 150 feet were placed on the caps of the columns. The bridge, with several spans, is 670 feet long. Concrete for the new deck was poured April 20. Barrier walls were poured April 28-29.
  • On May 5, westbound I-44 traffic was shifted to the eastbound side. The old bridge deck and girders were removed by May 13. Then substructure repairs were made to the old bridge.
  • Concrete extensions 8-1/2 feet long were added to the columns on the existing bridge to close the gap between the existing bridge and the temporary columns where the new 38-foot wide deck-and-gird assembly was built. That left only a 3/4-inch gap between the two structures.
  • "Sliders" were placed continuously across both sets of bridge columns. Sliders are stainless steel plates 2 feet wide and 10 feet long. Sliders were placed on top of the temporary bridge columns underneath the new girders and deck as they were built. Teflon bearing pads were attached to the bottom of the new girders to further ease the movement. Sliders also were placed on top of the columns of the existing bridge and across the 3/4-inch gap between the two bridges.
  • Seven hydraulic, "push-pull" jacks, powered by diesel generators, were set up, one jack on each of the new columns. The jacks "pushed" the new superstructure and then "pulled" themselves up to make next push.
  • On May 16, the new deck-and-girder assembly was slowly moved 45 feet -- from the temporary columns onto the columns of the existing bridge. The process began at 9 a.m. The move was completed at 7 p.m. The day included a four-hour delay to readjust sliders and make other corrections. During the sliding process, the new structure was moved 3 feet at a time because of the 3-foot stroke of the hydraulic jacks. Each 3-foot move took about one minute.
  • The move was made successfully with no damage to the new deck-and-girder structure as it was shifted into its permanent location on the columns of the existing bridge.
  • Dishwashing liquid was used as a lubricant to help ease the new deck-and-girder structure along the sliders. Workers, who bought 30 "economy size" jugs of dishwashing liquid at stores in Lebanon and St. Robert, liberally applied the liquid to the sliders as the jacks pushed.
  • Starting May 16, leading up to the May 23 bridge opening, workers replaced the teflon bearing pads with permanent weight bearing plates, laid asphalt on the highway approaches on each side of the bridge, installed new guardrail and cut in and painted rumble stripes.

For more information, contact our Springfield District Office at 417-895-7600 or 1-888-ASK-MoDOT (275-6636).

Last updated: June 2011


 
District Map
Southwest District
spacer
Traveler Information
Traveler Map
Ozarks Traffic
map
call, cell, mobile, phone iconText Alerts - Sign Up!
spacer
Quick Links
Your Local Area Engineer
Report a Road Concern
Moving Forward
Project Freeway: U.S. 60 Rogersville
On the Move
spacer
Your Local MoDOT
Get your local district information.
Districts Map
Northwest Northeast Kansas City Central St. Louis Southwest Southeast
About Us
How Do I...
Contact Us
Missouri Department of Transportation
Central Office
105 W. Capitol Avenue
Jefferson City, MO 65102
1-888-ASK-MODOT (275-6636)
1-866-831-6277 (Motor Carrier Services)
Drivers License Offices
horz_bar
| | |
Missouri State Government
 
© 2013 Missouri Department of Transportation. All Rights Reserved.   Privacy Policy.
 
 
Bates Vernon Barton Jasper Newton McDonald Barry Stone Taney Lawrence Dade Cedar St. Clair Henry Christian Greene Polk Hickory Benton Dallas Webster Northwest Northeast Kansas City Central St. Louis Southwest Southeast iTunes Android Facebook Twitter Flickr Google+ Blog YouTube RSS Facebook Twitter Flickr Google+ Blogspot YouTube RSS Feed