I-44/U.S. 65 Reconstruction: Springfield
Heads Up: The plan to close the westbound I-44-to-southbound Route 65 ramp on Thursday night, February 8, has been postponed. The nighttime ramp closing will be rescheduled for next week at the earliest.
Work scheduled:
* Installing bridge girders at night beginning Thursday night
* Completing a bridge column in the median of U.S. 65 south of I-44
* Tying reinforcing steel for future concrete pavement on the new northbound U.S. 65-to-eastbound I-44 ramp
Traffic Impacts:
* The westbound I-44-to-southbound U.S. 65 ramp closed between 11 p.m. and 5 a.m. Thursday night into Friday morning
* Dump trucks hauling dirt and rock traveling with traffic using U.S. 65 north of I-44
* Southbound U.S. 65-to-westbound I-44 ramp closed until late February
RAMP DETOUR: Southbound on U.S. 65 to eastbound I-44 ramp. Eastbound on I-44 to Route 744 (Mile Marker 84), go north over the bridge and then westbound on I-44
* The eastbound I-44-to-northbound U.S. 65 ramp closed until spring 2008
RAMP DETOUR: Eastbound on I-44 to Route 744 (Mile Marker 84), exit onto Route 744, go north over the bridge and then westbound on I-44 to northbound U.S. 65 ramp
* Northbound on-ramp at Kearney Street/U.S. 65 interchange narrowed to 10 feet
* Traffic using temporary northbound U.S. 65-to-eastbound I-44 ramp
* Eastbound and westbound I-44 traffic shifted toward median
* Northbound and southbound U.S. 65 traffic shifted toward median
* All other work taking place AWAY from traffic behind concrete barrier walls
Speed limit throughout project: 50 mph. Work zone speed limit being enforced on regular basis by local law enforcement officers.
The Project: * New directional "flyover" ramp: northbound U.S. 65-to-westbound I-44
* New northbound U.S. 65 bridge over I-44; rebuilding northbound lanes between Kearney Street and Valley Water Mill Road
* Rebuilding northbound-to-eastbound and southbound-to-westbound ramps
* Rebuilding eastbound I-44 lanes underneath U.S. 65
Scheduled completion: May 2008