Hollister/U.S. 65 Interchange
Construction
Update for Week of December 13
Work scheduled:
Rock blasting planned east side of U.S. 65 near Route
165.
Rock blasting planned at Birch Road and Industrial Boulevard.
Dirt graded and utilities relocated on east side of U.S. 65 along
Business 65 near First Street.
Utility lines relocated at Blue Sky Lane.
Impact on Traffic: When blasting occurs, traffic
on U.S. 65 will be stopped for short periods before and after
the blast. The scheduled delay for blasting is five minutes each
time, though it could be longer.
One-lane traffic and delays possible at intersection of Birch
Road and Industrial Boulevard.
Work zone speed limit on U.S. 65: 45 mph.
Project background: Construction of U.S. 65/Business
65 interchange and overpass for Business 65 north of new interchange
and widening of U.S. 65 to four lanes along 1.6 miles (2,000 feet
north of Bus. 65/Route V to just south of Route 165.)
Cost: $19.2 million (low bid), shared by MoDOT, City of Hollister
and Taney County.
Prime contractor: W.A. Ellis Construction of Independence.
Scheduled completion: Spring 2007