LAWERENCE COUNTY: Work continues throughout this week on the I-44/Route 39 interchange as eastbound traffic is routed up and over the Exit 46 ramp as crews remove the old bridge structure. The work is scheduled overnight, from 9 p.m. through 6 a.m.
Traffic was moved onto the new bridge and new northbound lanes of Route 39 on October 16.
APAC-Missouri of Columbia was awarded the $6.3 million contract to replace the bridge with a 5-lane bridge, realign the south outer road and add signals.
The project remains on-schedule, with an estimated completion date of Nov. 25, 2009.
###