Hollister/U.S. 65 Interchange Construction
Traffic Alert and Update for Week of January 31

Traffic Alert: Gage Drive at Highway 65 near the Hollister Police Department scheduled to be closed during the day on Thursday and Friday, February 3 and 4. The entrance reopened at night. Crews installing a drain pipe across Gage Drive. Drivers will have to find an alternate route around the closing. The work may be postponed due to rain or snow. -- Work Postponed Due to Snow.

Work scheduled: Additional blasting site added to schedule. Rock blasting planned east side of U.S. 65 north of the Route V/Business 65 intersection, east side of Route 65 near Route 165 and on either side of Route 65 south of Mall Road.
Birch Road remains closed north of Industrial Boulevard until mid-March. Installing a box culvert across the road and relocating utility lines.
Rock and dirt hauling at night across Business 65 east of Route 65. Dirt and rock being used to build new interchange ramps.
Utility line relocation on Blue Sky Lane.
Utility line relocations planned along Industrial Boulevard near Birch Road.

Impact on Traffic: During blasting operations, traffic on U.S. 65 will be stopped for short periods before and after the blast. The scheduled delay for blasting is five minutes each time, though it could be longer. Blasting may occur several times a day at all three locations.
Drivers using Birch Road will have to find alternate routes around the road closing.
Traffic will continue to be stopped at night between 7 p.m. and 5 a.m. on Business 65 east of Route 65. Traffic stops will be brief to allow dump trucks to cross the road.
Traffic shifted to a temporary bypass on Blue Sky Lane near Herrman Lumber Company as crews relocate a utility line.
Delays are possible on Industrial Boulevard near Birch Road.
All other work planned should take place AWAY from traffic.

Work zone speed limit on U.S. 65: 45 mph.

Project background: Construction of U.S. 65/Business 65 interchange and overpass for Business 65 north of new interchange and widening of U.S. 65 to four lanes along 1.6 miles (2,000 feet north of Bus. 65/Route V to just south of Route 165.)
Cost: $19.2 million (low bid), shared by MoDOT, City of Hollister and Taney County.
Prime contractor: W.A. Ellis Construction of Independence.
Scheduled completion: Fall 2006.

 

 

 

 

 

 
District Map
Southwest District
spacer
Traveler Information
Traveler Map
Ozarks Traffic
map
call, cell, mobile, phone iconText Alerts - Sign Up!
spacer
Quick Links
Report a Road Concern
Media Inquiries
Your Local Area Engineer
Route 65: THE REBUILD
spacer
Your Local MoDOT
Get your local district information.
Districts Map
Northwest Northeast Kansas City Central St. Louis Southwest Southeast
About Us
How Do I...
Contact Us
Missouri Department of Transportation
Central Office
105 W. Capitol Avenue
Jefferson City, MO 65102
1-888-ASK-MODOT (275-6636)
1-866-831-6277 (Motor Carrier Services)
Drivers License Offices
horz_bar
| | |
Missouri State Government
 
© 2013 Missouri Department of Transportation. All Rights Reserved.   Privacy Policy.
 
 
Bates Vernon Barton Jasper Newton McDonald Barry Stone Taney Lawrence Dade Cedar St. Clair Henry Christian Greene Polk Hickory Benton Dallas Webster Northwest Northeast Kansas City Central St. Louis Southwest Southeast iTunes Android Facebook Twitter Flickr Instagram Blog YouTube RSS Facebook Twitter Flickr Google+ Blogspot YouTube RSS Feed