November 17, 2017 07:43 AM
Chestnut Railroad Bridge Project in Springfield
Update for Week of November 20
  • EARLY HEADS UP: Chestnut Expressway CLOSED Friday-Monday, Dec. 1-4, at railroad bridge to allow crews to pour concrete for remaining 1/3 of bridge. Traffic will be detoured during the closing. 

Work Scheduled:  

  • Building business entrance on north side of Chestnut Expressway at Ingram Mill Road
  • Installing curb and gutter along McDaniel Street north of new bridge
  • Building retaining walls in areas on north side of bridge
  • Prepping bridge for Dec. 1-4 concrete pour 

Traffic Impacts:  

  • EARLY TRAFFIC ALERT: Chestnut Expressway CLOSED between Belcrest Avenue and Ingram Mill Road
    • Work hours: 6 p.m. Friday, Dec. 1, until as late as 6 a.m. Monday, Dec. 4
    • Signed detour: Belcrest Avenue, Cairo Street, Union Avenue, Cherry Street and Ingram Mill Road
    • Contractor crews pouring concrete for north 1/3 of railroad bridge
    • Access will remain open to all businesses in the area
  • CHESTNUT EXPRESSWAY TRAFFIC USING NEW RAILROAD BRIDGE:
    • Two westbound lanes open
    • One eastbound lane open
    • Delays occurring eastbound on Chestnut Expressway during afternoon rush hour
    • Drivers urged to use both eastbound lanes of Chestnut Expressway leading up to new bridge and then take turns merging into one lane near Belcrest Avenue
  • Drivers will need to use Rockhurst Street (take Belcrest Avenue one block north of Chestnut Expressway) to reach businesses in Chestnut Warehouse complex. Business entrance from Chestnut Expressway temporarily closed to make way for north 1/3 of new railroad bridge and to raise elevation for future business entrance.
  • McDaniel Street underneath new bridge open to traffic
  • Camera view of project 

(Weather or construction delays could alter the work schedule.) 

Project Summary:

  • Build a bridge on Chestnut Expressway over the railroad tracks west of Route 65
  • Build new roads on either side of Chestnut Expressway to provide access to area businesses
  • Install a new traffic signal at Ingram Mill Road and Chestnut Expressway
  • First phase of construction: June to December 2016. Prime contractor: D&E Blasting & Excavating, Nixa -- COMPLETED
  • Second phase of construction: January 2017 to November 2017. Prime contractor: Lehman Construction Company, California 
  • Partnership project: Springfield, Greene County, Burlington Northern-Santa Fe Railroad & MoDOT
  • Completion Date: Late 2017
  • Total Project Cost: $14.8 million

 END 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest

(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)

(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)

Links to related information:

 

 
District Map
Southwest District
spacer
Traveler Information
Traveler Map
Ozarks Traffic
map
call, cell, mobile, phone iconText Alerts - Sign Up!
spacer
Quick Links
Report a Road Concern
Media Inquiries
Your Local Area Engineer
Route 65: THE REBUILD
spacer
Your Local MoDOT
Get your local district information.
Districts Map
Northwest Northeast Kansas City Central St. Louis Southwest Southeast
About Us
How Do I...
Contact Us
Missouri Department of Transportation
Central Office
105 W. Capitol Avenue
Jefferson City, MO 65102
1-888-ASK-MODOT (275-6636)
1-866-831-6277 (Motor Carrier Services)
Drivers License Offices
horz_bar
| | |
Missouri State Government
 
© 2013 Missouri Department of Transportation. All Rights Reserved.   Privacy Policy.
 
 
Bates Vernon Barton Jasper Newton McDonald Barry Stone Taney Lawrence Dade Cedar St. Clair Henry Christian Greene Polk Hickory Benton Dallas Webster Northwest Northeast Kansas City Central St. Louis Southwest Southeast iTunes Android Facebook Twitter Flickr Instagram Blog YouTube RSS Facebook Twitter Flickr Google+ Blogspot YouTube RSS Feed