U.S. Route 60 at Greene County Routes NN/J Interchange Project
Update for Week of July 11, 2016
  • Greene County Route J and Greene County Farm Roads 195 and 199 CLOSED
  • Westbound Route 60 shifted to new lanes at Route J 

Work Scheduled:  

  • Grinding and removing old sections of westbound Route 60 at Route J
  • Installing box culverts on the north side of Route 60
  • Excavating for bridge footings on the north side of Route 60 

Traffic Impacts:  

  • TRAFFIC SHIFT: Westbound lanes of Route 60 shifted to new lanes on either side of Route J
  • ROAD CLOSINGS:
    • Route J CLOSED at Route 60 to allow crews to connect it to new interchange
    • Farm Road 195 CLOSED at Route 60 to allow crews to connect to new outer road
    • Farm Road 199 CLOSED at Route 60 permanently
  • Temporary Traffic Pattern at Route NN:
    • Eastbound ramps OPEN from Route 60 to Route NN and from Route NN to Route 60
    • Drivers must use median crossovers at Farm Road 193 and Farm Road 205 to reach desired direction
    • Old section of Route NN at Route 60 closed permanently
    • Traffic pattern remains in place until interchange opens in fall 2016
  • Route 60 Median Crossovers CLOSED Permanently:
    • At Route NN/J
    • At Farm Road 199
    • At Farm Road 203
  • No traffic impacts for eastbound Route 60
  • While lanes on Route 60 may be closed at times, one lane in each direction will remain open at all times.
  • Work zone speed limit reduced to 50 mph
  • Crews and equipment entering and leaving work areas

 

 (Weather or construction delays could alter the work schedule.)

Project Summary:

  • Build new diamond interchange east of existing at-grade intersection between Springfield and Rogersville
  • Build new section of westbound Route 60 between Greene County Farm Roads 205 and 193
  • Convert a section of westbound Route 60 to an outer road between Farm Road 195 and Route J

Prime Contractor: Emery Sapp and Sons, Columbia

Completion Date: November 2016

Total Project Cost: $15.1 million.

Follow MoDOT's Southwest District:

  • Facebook: MoDOT.Southwest
  • Twitter: MoDOT_Southwest
  • Instagram: @MoDOT_Southwest
Links to related information:

 

 
District Map
Southwest District
spacer
Traveler Information
Traveler Map
Ozarks Traffic
map
call, cell, mobile, phone iconText Alerts - Sign Up!
spacer
Quick Links
Report a Road Concern
Media Inquiries
Your Local Area Engineer
Route 65: THE REBUILD
spacer
Your Local MoDOT
Get your local district information.
Districts Map
Northwest Northeast Kansas City Central St. Louis Southwest Southeast
About Us
How Do I...
Contact Us
Missouri Department of Transportation
Central Office
105 W. Capitol Avenue
Jefferson City, MO 65102
1-888-ASK-MODOT (275-6636)
1-866-831-6277 (Motor Carrier Services)
Drivers License Offices
horz_bar
| | |
Missouri State Government
 
© 2013 Missouri Department of Transportation. All Rights Reserved.   Privacy Policy.
 
 
Bates Vernon Barton Jasper Newton McDonald Barry Stone Taney Lawrence Dade Cedar St. Clair Henry Christian Greene Polk Hickory Benton Dallas Webster Northwest Northeast Kansas City Central St. Louis Southwest Southeast iTunes Android Facebook Twitter Flickr Instagram Blog YouTube RSS Facebook Twitter Flickr Google+ Blogspot YouTube RSS Feed