Project Freeway: U.S. 60 Rogersville
Update for Week of June 13, 2016
  • Shifting Webster County Route V traffic to the east to begin widening work on the west side of the road 

 

Work Scheduled:  

  • Route B/VV at Route 60
    • Grading work along the west side of Route VV south of Route 60
    • Rebuilding business entrances along Route V
    • Pouring concrete for curb and gutter along Route V
  • Route 60 at Greene County Farm Road 253 Interchange
    • Pouring concrete for middle portion and curbs on new roundabouts north and south of Route 60
    • Grading dirt and rock for ramps along Route 60
  • Route 60 at Greene County Farm Road 247 Interchange
    • Hauling rock and dirt to build up areas on either end of new bridge 

Traffic Impacts:  

  • NEW TRAFFIC SHIFT: Route V traffic shifted to east south of Route 60
  • Business entrances narrowed or closed on west side of Route V south of Route 60. However, drivers may have to travel over gravel to get into and out of business entrances. Access remains open to ALL businesses.
  • Greene County Farm Road 253 south of Route 60 CLOSED along with the Route 60 median crossover
  • Crews and equipment entering and leaving work areas, especially along Route 60 at Greene County Farm Roads 247 and 253 

(Weather or construction delays could alter the work schedule.) 

Project Summary:

  • Build an interchange at Route 60 and Routes B/VV
  • Build an interchange at Route 60 and Farm Road 253
  • Build an overpass over Route 60 at Farm Road 247
  • Build turn lanes on Route 60 at Chicory Road and at Peck Hollow Road -- COMPLETED
  • Widen Farm Road 253 between Route 60 and Center Street
  • Reconfigure intersection of Route VV and Redbud Street
  • Improve the intersection of Route VV and Johnstown Drive
  • Build outer roads in areas to connect Rogersville streets to new interchanges

Design-Build Contractor: Ozark Regional Road Constructors

Completion Date: December 2016

Total Project Cost: $35 million

Follow MoDOT's Southwest District:

  • Facebook: MoDOT.Southwest
  • Twitter: MoDOT_Southwest
  • Instagram: @MoDOT_Southwest
Links to related information:

 

 
District Map
Southwest District
spacer
Traveler Information
Traveler Map
Ozarks Traffic
map
call, cell, mobile, phone iconText Alerts - Sign Up!
spacer
Quick Links
Report a Road Concern
Media Inquiries
Your Local Area Engineer
Route 65: THE REBUILD
spacer
Your Local MoDOT
Get your local district information.
Districts Map
Northwest Northeast Kansas City Central St. Louis Southwest Southeast
About Us
How Do I...
Contact Us
Missouri Department of Transportation
Central Office
105 W. Capitol Avenue
Jefferson City, MO 65102
1-888-ASK-MODOT (275-6636)
1-866-831-6277 (Motor Carrier Services)
Drivers License Offices
horz_bar
| | |
Missouri State Government
 
© 2013 Missouri Department of Transportation. All Rights Reserved.   Privacy Policy.
 
 
Bates Vernon Barton Jasper Newton McDonald Barry Stone Taney Lawrence Dade Cedar St. Clair Henry Christian Greene Polk Hickory Benton Dallas Webster Northwest Northeast Kansas City Central St. Louis Southwest Southeast iTunes Android Facebook Twitter Flickr Instagram Blog YouTube RSS Facebook Twitter Flickr Google+ Blogspot YouTube RSS Feed