Project Freeway: U.S. 60 Rogersville
Update for Week of March 21, 2016
  • Greene County Farm Road 243 south of U.S. Route 60 scheduled to close for three days starting March 24
  • Paving work planned for connector roads/interchange ramps over next two weeks 

 

Work Scheduled:  

  • Route 60 and Webster County Routes B/VV Interchange
    • Relocating utilities for center-turn lane construction on Route VV south of Route 60
  • Route 60 at Greene County Farm Road 247 Interchange:
    • Installing components for bridge deck/driving surface
    • Grading and placing rock for interchange ramps
  • Route 60 at Greene County Farm Road 253 Interchange
    • Placing rock for interchange ramps
    • Paving ramps
    • Installing wiring for street lights at interchange
  • Paving Johnstown Road extension south of Route 60 near Farm Road 253
  • Paving Center Street extension south of Route 60 from Farm Road 243 to the east

Traffic Impacts:  

  • ROAD CLOSING: Farm Road 243 north of Route 60 will be CLOSED for up to three days starting Thursday, March 24, for paving of Center Street extension. Drivers urged to find alternate route during the closing. Weather could force the closing to be rescheduled to a later date.
  • Daytime lane closings on Route 60 at Farm Road 247. Work hours: 9 a.m. until 3 p.m.
  • Greene County Farm Road 253 south of Route 60 CLOSED along with the Route 60 median crossover
  • Crews and equipment entering and leaving work areas

(Weather or construction delays could alter the work schedule.)

Project Summary:

  • Build an interchange at Route 60 and Routes B/VV
  • Build an interchange at Route 60 and Farm Road 253
  • Build an overpass over Route 60 at Farm Road 247
  • Build turn lanes on Route 60 at Chicory Road and at Peck Hollow Road -- COMPLETED
  • Widen Farm Road 253 between Route 60 and Center Street
  • Reconfigure intersection of Route VV and Redbud Street
  • Improve the intersection of Route VV and Johnstown Drive
  • Build outer roads in areas to connect Rogersville streets to new interchanges

Design-Build Contractor: Ozark Regional Road Constructors

Completion Date: December 2016

Total Project Cost: $35 million 

To learn more about MoDOT’s direction and funding shortfalls, subscribe to View from the Chair.

Follow MoDOT's Southwest District:

  • Facebook: MoDOT.Southwest
  • Twitter: MoDOT_Southwest
  • Instagram: @MoDOT_Southwest
Links to related information:

 

 
District Map
Southwest District
spacer
Traveler Information
Traveler Map
Ozarks Traffic
map
call, cell, mobile, phone iconText Alerts - Sign Up!
spacer
Quick Links
Report a Road Concern
Media Inquiries
Your Local Area Engineer
Route 65: THE REBUILD
spacer
Your Local MoDOT
Get your local district information.
Districts Map
Northwest Northeast Kansas City Central St. Louis Southwest Southeast
About Us
How Do I...
Contact Us
Missouri Department of Transportation
Central Office
105 W. Capitol Avenue
Jefferson City, MO 65102
1-888-ASK-MODOT (275-6636)
1-866-831-6277 (Motor Carrier Services)
Drivers License Offices
horz_bar
| | |
Missouri State Government
 
© 2013 Missouri Department of Transportation. All Rights Reserved.   Privacy Policy.
 
 
Bates Vernon Barton Jasper Newton McDonald Barry Stone Taney Lawrence Dade Cedar St. Clair Henry Christian Greene Polk Hickory Benton Dallas Webster Northwest Northeast Kansas City Central St. Louis Southwest Southeast iTunes Android Facebook Twitter Flickr Instagram Blog YouTube RSS Facebook Twitter Flickr Google+ Blogspot YouTube RSS Feed